VENµS MISSION STATUS VENµS users meeting – Jan 2010 Pierric FERRIER, CNES pied de page /
Content 1 - Camera status 2 - Bus status 3 - Ground segment status 4 - Launcher status 5 - Summary VENµS users meeting – Jan 2010 2
1 - Camera status Camera longitudinal section SUN SHIELD THERMAL CONTROL SHIELD BEZEL DETECTORS ASSEMBLY TUBE SMA VENµS users meeting – Jan 2010 PMA CEU CORRECTION LENSES 3
1 - Camera status Tube equipped with both mirrors VENµS users meeting – Jan 2010 4
1 - Camera status Correction lens assembly VENµS users meeting – Jan 2010 5
1 - Camera status Thermal control shield (external cylinder) VENµS users meeting – Jan 2010 6
1 - Camera status ~ 1. 4 mm Blocking Filter 2. 0 mm Camera status synthesis Narrow-band Filters 8. 0 mm 10 mm BARR filters= the weakest link of the chain, so far. . . • 18 months needed to obtain the ITAR approval • 13 months delay in manufacturing due to technical issues (delivery expected in March) The current schedule shows a camera delivery at end of Aug 2011 VENµS users meeting – Jan 2010 7
2– Bus status - Mass: 250 kg - 2 x. STR - Power: 800 w - 2 X-band - Overall stowed dim: 1. 6 x 1. 2 m - 1 x. IHET redunded , 16 Kg Xenon - 4 x 1 N redunded thrusters, 7 Kg hydrazine VENµS users meeting – Jan 2010 8
2– Bus status VENµS users meeting – Jan 2010 9
2– Bus status VENµS users meeting – Jan 2010 10
2– Bus status VENµS users meeting – Jan 2010 11
2– Bus status synthesis • Base plate to be delivered this quarter (from RAFAEL to IAI) • Other parts of the bus are stored and ready for final bus assembly (solar pannel, satellites pannels - 6 of them, and all bus internal subsystems) VENµS users meeting – Jan 2010 12
3– Ground segment status Satellite command & control and technological mission ISRAEL Ready end of 2010 VENµS users meeting – Jan 2010 Scientific mission FRANCE Ready end of 2010 13
4– Launcher status The foreseen launcher for Venµs is PSLV so far. Unfortunately this scenario faces 2 issues • at the INDIAN government level • as Venµs would be the co-passenger, the risk exist to be injected in a non optimal orbit (i. e. 666 km – 3 days instead of 720 km -2 days) • Nevertheless, other scenarios exist, the main one being a launch with PLEIADES 2 on SOYOUZ • Current engineering practice calls for a final launcher selection 2 years ahead of the foreseen launch date. In other words the launcher will be selected in 2010. VENµS users meeting – Jan 2010 14
5 - Summary Mission timeline 2009 CAMERA 2010 2011 2012 …… 2015 last quarter MISSION GROUND SEGMENT IHET SATELLITE mid year GROUND CONTROL SEGMENT MISSION VENµS users meeting – Jan 2010 15