U. S. ITER Project STEADY STATE ELECTRIC POWER NETWORK (SSEPN) Charles Neumeyer SSEPN Team Leader Princeton Plasma Physics Laboratory 1 st Information Forum Vendor Fair November 15, 2006 Steady State Electric Power Network PPPL
ITER AC Power Systems Steady State Electric Power Network EU + US 120 MW 50 MVAR 130 MVA Continuous 400 k. V Host (EU) Pulsed Electric Power Network 500 MW 400 MVAR 650 MVA Pulsed EU + China ~ ~ Class IV: CWS 37 MW Cryo 27 MW Other 50 MW Class III (Safety): 8 MW Steady State Electric Power Network = Magnets 2 ~ = P, Q Control Heating & Current Drive PPPL
ITER AC Power Systems Steady State Electric Power Network EU + US 120 MW 50 MVAR 130 MVA Continuous 400 k. V Host (EU) Pulsed Electric Power Network 500 MW 400 MVAR 650 MVA Pulsed EU + China Similar to auxiliary electrical system of nuclear power plant except higher power level ~ ~ Class IV: CWS 37 MW Cryo 27 MW Other 50 MW Class III (Safety): 8 MW Steady State Electric Power Network = Magnets 3 ~ = P, Q Control Heating & Current Drive PPPL
Status of SSEPN Activities • Conceptual design was developed for a generic site in 2001 • Conceptual design was updated in 2004 • Decisions on site selection and scope sharing made in 2005 • Preliminary design activity based on French site now beginning Steady State Electric Power Network 4 PPPL
SSEPN Roles of US & EU TASK EU ROLE US ROLE Engineering Design Lead Monitor Cabling 100% Diesel Generators & UPS systems 100% All other equipment from 400 k. V grid to consumer interface 25% Installation & Commissioning Lead Steady State Electric Power Network 5 75% PPPL
ITER AC Power Systems: One Line Diagram Grid Operator SSEPN Steady State Electric Power Network PEPN 6 PPPL
SSEPN One Line Diagram Steady State Electric Power Network 7 PPPL
SSEPN Equipment HV Switchgear HV Transformers MV Switchgear MV Cabling Diesel Generators MV Transformers LV Load Centers LV Distribution Boards LV Cabling Steady State Electric Power Network 8 PPPL
Equipment Split by US (75%) & EU (25%) HV Switchgear HV Transformers MV Switchgear MV Transformers LV Load Centers LV Distribution Boards Steady State Electric Power Network 9 PPPL
Equipment Procurement • It is anticipated (but not yet agreed) that: - cost estimate will be updated after preliminary design completion - groups of equipment will be assigned to US and EU for 75: 25 split HV Switchgear HV Transformers MV Switchgear MV Transformers LV Load Centers LV Distribution Boards - credit for US-EU inbalance amount will be agreed to • Equipment will be built to IEC standards for installation in France • Special requirements for nuclear installation not anticipated TBD (i. e. not Class 1 E like a fission plant) • Equipment to be delivered to ITER site in France Steady State Electric Power Network 10 PPPL
Participants and Roles within US Activity • Administration US ITER Project - Liaison w/International Team - Monitor Engineering Design Activities - Oversight of E/C contract - Oversight of Procurements • Engineering Subcontract to Engineering/ Construction Firm - E/C Contract to: § prepare procurement specifications § solicit bids § perform bid evaluation § make purchase recommendation § award and execute contracts § provide QC and test witnessing at factories § arrange shipping § provide QC receipt inspection at ITER site • Procurement Equipment Manufacturers • Fabrication & Delivery Steady State Electric Power Network PPPL
Schedule = activity involving US ü 12 months for procurement ü 18 months for fabrication ü 24 months for installation ü 12 months for commissioning Steady State Electric Power Network PPPL
Summary • SSEPN is a conventional AC power substation & distribution system • US will procure 75% of equipment (except cables, D/G, and UPS) • Work will flow through an E/C firm to equipment manufacturers • Equipment will be per IEC standards for delivery and installation in France • Procurement/fabrication phase over 30 month period beginning 2010 Steady State Electric Power Network 13 PPPL
Opportunities for Participation • More information about design, etc. , is available via C. Neumeyer • Close contact with industry is sought to facilitate planning & budgeting!! Steady State Electric Power Network 14 PPPL