Strategic Importance of Project Management
Strategic Importance of Project Management continued
Project Characteristics
An Example
An Example
An Example
What is a project?
Formal definition
Management of Large Projects
Project Planning, Scheduling, and Controlling
Project Planning
Project planning process
Project Organization
A Sample Project Organization
Matrix Organization
The Role of the Project Manager
Work Breakdown Structure
Project Scheduling
Project Scheduling Techniques
Gantt Chart
Project Control Reports
PERT and CPM
The Six Steps Common to PERT & CPM
Network Terms
Activity Relationships
Activity Relationships
Activity Relationships
Dummy Activities
Dummy Activity Example
PERT Activity Times
Critical Path Analysis
Earliest Start and Finish Steps
Latest Start and Finish Steps
Critical Path in Network
Gantt Chart Earliest Start and Finish
Gantt Chart Latest Start and Finish
Project Times
An example
Activity Slack
Activity Slack
Activity Slack
Activity Slack
Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65
Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65
Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 weeks @ $1, 000/week
Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 weeks @ $1, 000/week 3($28, 000) – 3($1, 000) = $81, 000
Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity J by 3 weeks @ $1, 000/week 3($28, 000) – 3($1, 000) = $81, 000 $2, 624, 000 – $81, 000 = $2, 543, 000
Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity J by 3 weeks @ $1, 000/week 3($28, 000) – 3($1, 000) = $81, 000 $2, 624, 000 – $81, 000 = $2, 543, 000
Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 weeks @ $1, 000/week 3($28, 000) – 3($1, 000) = $81, 000 $2, 624, 000 – $81, 000 = $2, 543, 000
Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 weeks @ $1, 000/week 3($28, 000) – 3($1, 000) = $81, 000 $2, 624, 000 – $81, 000 = $2, 543, 000
Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity D by 2 weeks @ $2, 000/week
Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000
Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 64 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000
Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000
Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000
Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 64 weeks Crash Activity K by 1 week @ $4, 000/week
Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 64 weeks Crash Activity K by 1 week @ $4, 000/week $8, 000 – $4, 000 = $4, 000 $2, 511, 000 – $4, 000 = $2, 507, 000
Total cost = $2, 624, 000 $2, 507, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activity K by 1 week @ $4, 000/week $8, 000 – $4, 000 = $4, 000 $2, 511, 000 – $4, 000 = $2, 507, 000
Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000
Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000
Total cost = $2, 624, 000 $2, 507, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activities B and C by 2 weeks @ $7, 000/week and $600/week
Total cost = $2, 624, 000 $2, 507, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activities B and C by 2 weeks @ $7, 000/week and $600/week 2($8, 000) – 2($7, 600) = $800 $2, 507, 000 – $800 = $2, 506, 200
Total cost = $2, 624, 000 $2, 506, 200 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 61 weeks Crash Activities B and C by 2 weeks @ $7, 000/week and $600/week 2($8, 000) – 2($7, 600) = $800 $2, 507, 000 – $800 = $2, 506, 200
Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000
Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000
Probabilistic Time Estimates
Probabilistic Time Estimates
Probabilistic Time Estimates 7 + 4(8) + 15 6
Probabilistic Time Estimates 7 + 4(8) + 15 6 15 - 7 6
Probabilities Critical Path = B - D - H - J - K
Probabilities Critical Path = B - D - H - J - K
Probabilities Critical Path = B - D - H - J - K
Probabilities Critical Path = B - D - H - J - K 72 – 69 11. 89
Probabilities Critical Path = B - D - H - J - K 72 – 69 11. 89
Probabilities Critical Path = B - D - H - J - K 72 – 69 11. 89
Probabilities Critical Path = B - D - H - J - K 72 - 69 11. 89
Probabilities Path = A - C - G - J - K 72 – 67 15. 55
Activity Duration Earliest Start Latest Start Slack C G J K D H E I F 10 35 4 6 10 40 24 15 10 16 26 61 65 10 20 10 16 16 14 24 59 63 9 19 35 48 53 – 2 – 2 – 1 25 32 37