Скачать презентацию Strategic Importance of Project Management Strategic Importance Скачать презентацию Strategic Importance of Project Management Strategic Importance

fe291de1e47862664ac2974a7d66f60c.ppt

  • Количество слайдов: 148

Strategic Importance of Project Management Strategic Importance of Project Management

Strategic Importance of Project Management continued Strategic Importance of Project Management continued

Project Characteristics Project Characteristics

An Example An Example

An Example An Example

An Example An Example

What is a project? What is a project?

Formal definition Formal definition

Management of Large Projects Management of Large Projects

Project Planning, Scheduling, and Controlling Project Planning, Scheduling, and Controlling

Project Planning Project Planning

Project planning process Project planning process

Project Organization Project Organization

A Sample Project Organization A Sample Project Organization

Matrix Organization Matrix Organization

The Role of the Project Manager The Role of the Project Manager

Work Breakdown Structure Work Breakdown Structure

Project Scheduling Project Scheduling

Project Scheduling Techniques Project Scheduling Techniques

Gantt Chart Gantt Chart

Project Control Reports Project Control Reports

PERT and CPM PERT and CPM

The Six Steps Common to PERT & CPM The Six Steps Common to PERT & CPM

Network Terms Network Terms

Activity Relationships Activity Relationships

Activity Relationships Activity Relationships

Activity Relationships Activity Relationships

Dummy Activities Dummy Activities

Dummy Activity Example Dummy Activity Example

PERT Activity Times PERT Activity Times

Critical Path Analysis Critical Path Analysis

Earliest Start and Finish Steps Earliest Start and Finish Steps

Latest Start and Finish Steps Latest Start and Finish Steps

Critical Path in Network Critical Path in Network

Gantt Chart Earliest Start and Finish Gantt Chart Earliest Start and Finish

Gantt Chart Latest Start and Finish Gantt Chart Latest Start and Finish

Project Times Project Times

An example An example

Activity Slack Activity Slack

Activity Slack Activity Slack

Activity Slack Activity Slack

Activity Slack Activity Slack

Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65

Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65

Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 weeks @ $1, 000/week

Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 weeks @ $1, 000/week 3($28, 000) – 3($1, 000) = $81, 000

Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = Total cost = $2, 624, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity J by 3 weeks @ $1, 000/week 3($28, 000) – 3($1, 000) = $81, 000 $2, 624, 000 – $81, 000 = $2, 543, 000

Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity J by 3 weeks @ $1, 000/week 3($28, 000) – 3($1, 000) = $81, 000 $2, 624, 000 – $81, 000 = $2, 543, 000

Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 weeks @ $1, 000/week 3($28, 000) – 3($1, 000) = $81, 000 $2, 624, 000 – $81, 000 = $2, 543, 000

Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 weeks @ $1, 000/week 3($28, 000) – 3($1, 000) = $81, 000 $2, 624, 000 – $81, 000 = $2, 543, 000

Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity D by 2 weeks @ $2, 000/week

Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 543, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000

Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 64 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000

Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000

Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000

Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 64 weeks Crash Activity K by 1 week @ $4, 000/week

Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 64 weeks Crash Activity K by 1 week @ $4, 000/week $8, 000 – $4, 000 = $4, 000 $2, 511, 000 – $4, 000 = $2, 507, 000

Total cost = $2, 624, 000 $2, 507, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 507, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activity K by 1 week @ $4, 000/week $8, 000 – $4, 000 = $4, 000 $2, 511, 000 – $4, 000 = $2, 507, 000

Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000

Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000

Total cost = $2, 624, 000 $2, 507, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 507, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activities B and C by 2 weeks @ $7, 000/week and $600/week

Total cost = $2, 624, 000 $2, 507, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 507, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activities B and C by 2 weeks @ $7, 000/week and $600/week 2($8, 000) – 2($7, 600) = $800 $2, 507, 000 – $800 = $2, 506, 200

Total cost = $2, 624, 000 $2, 506, 200 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 506, 200 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 61 weeks Crash Activities B and C by 2 weeks @ $7, 000/week and $600/week 2($8, 000) – 2($7, 600) = $800 $2, 507, 000 – $800 = $2, 506, 200

Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000

Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Total cost = $2, 624, 000 $2, 511, 000 Indirect costs = $8, 000/week Penalty cost = $20, 000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 weeks @ $2, 000/week $28, 000 + $8, 000 – 2($2, 000) = $32, 000 $2, 543, 000 – $32, 000 = $2, 511, 000

Probabilistic Time Estimates Probabilistic Time Estimates

Probabilistic Time Estimates Probabilistic Time Estimates

Probabilistic Time Estimates 7 + 4(8) + 15 6 Probabilistic Time Estimates 7 + 4(8) + 15 6

Probabilistic Time Estimates 7 + 4(8) + 15 6 15 - 7 6 Probabilistic Time Estimates 7 + 4(8) + 15 6 15 - 7 6

Probabilities Critical Path = B - D - H - J - K Probabilities Critical Path = B - D - H - J - K

Probabilities Critical Path = B - D - H - J - K Probabilities Critical Path = B - D - H - J - K

Probabilities Critical Path = B - D - H - J - K Probabilities Critical Path = B - D - H - J - K

Probabilities Critical Path = B - D - H - J - K 72 Probabilities Critical Path = B - D - H - J - K 72 – 69 11. 89

Probabilities Critical Path = B - D - H - J - K 72 Probabilities Critical Path = B - D - H - J - K 72 – 69 11. 89

Probabilities Critical Path = B - D - H - J - K 72 Probabilities Critical Path = B - D - H - J - K 72 – 69 11. 89

Probabilities Critical Path = B - D - H - J - K 72 Probabilities Critical Path = B - D - H - J - K 72 - 69 11. 89

Probabilities Path = A - C - G - J - K 72 – Probabilities Path = A - C - G - J - K 72 – 67 15. 55

Activity Duration Earliest Start Latest Start Slack C G J K D H E Activity Duration Earliest Start Latest Start Slack C G J K D H E I F 10 35 4 6 10 40 24 15 10 16 26 61 65 10 20 10 16 16 14 24 59 63 9 19 35 48 53 – 2 – 2 – 1 25 32 37