Скачать презентацию Software Project Planning Software Engineering Estimation n Скачать презентацию Software Project Planning Software Engineering Estimation n

c78fb57ca7ccfafe48abe407aa25f965.ppt

  • Количество слайдов: 19

Software Project Planning Software Project Planning

Software Engineering Estimation n The SPM begins with a set of activities that are Software Engineering Estimation n The SPM begins with a set of activities that are collectively called Project planning n Whenever estimates are made we look into future concern and so there is some degree of uncertainty in estimation n

Software Engineering n n Observation on Estimation PM manager must have the ability to Software Engineering n n Observation on Estimation PM manager must have the ability to estimate PM with the ability to know what will go wrong before it actually does Estimation of resources, cost and schedule for a software requires experience of past projects and access to historical data

Software Engineering Project complexity has a strong effect on uncertainty that is inherent in Software Engineering Project complexity has a strong effect on uncertainty that is inherent in planning. n Complexity is affected by familiarity with past efforts n Real time projects are always complex n Project size also effect the accuracy of the estimates n

Software Engineering n If the requirements have been solidified estimation is easy but if Software Engineering n If the requirements have been solidified estimation is easy but if the requirement are keep on changing estimation is affects

Software Engineering Project Planning objectives n The objectives of software project planning is to Software Engineering Project Planning objectives n The objectives of software project planning is to provides the reasonable estimates of cost, effort and schedule n These estimates are made at the beginning of the project and must be updated wit the passage of time. n

Software Engineering Software Scope n Estimation of scope n Functional, non functional requirements. Constraints Software Engineering Software Scope n Estimation of scope n Functional, non functional requirements. Constraints n

Software Engineering Obtaining information necessary for scope n Things are always hazy at the Software Engineering Obtaining information necessary for scope n Things are always hazy at the start of the project n There must be some meeting between customer and analyst for obtaining the scope of project n

Software Engineering 1 st meeting question n 2 nd meeting question n 3 rd Software Engineering 1 st meeting question n 2 nd meeting question n 3 rd meeting question and so on n

Software Engineering n Resources n The 2 nd task of software planning is the Software Engineering n Resources n The 2 nd task of software planning is the estimation of resources required to accomplish the software development effort Pyramid The development environment-----Hardware and software tools, Reusable components and people n n

Software Engineering n n Human Resource: The no. of people required for a software Software Engineering n n Human Resource: The no. of people required for a software project can be determined only after an estimate of development effort. Reusable Software component Off the shelf components Full experience components Partial experience components New components

Software Engineering n Guidelines Software Engineering n Guidelines

Software Engineering n Software Sizing Fuzzy logic sizing Function point sizing Standard component sizing Software Engineering n Software Sizing Fuzzy logic sizing Function point sizing Standard component sizing

Software Engineering n Problem based estimation EV is calculated as EV= (Sopt+4 Sm+Spess)/6 There Software Engineering n Problem based estimation EV is calculated as EV= (Sopt+4 Sm+Spess)/6 There is a very small probability that the actual size result will fall outside the EV

Software Engineering n Example Software Engineering n Example

Software Engineering n COCOMO Model Constructive Cost model Three model Model 1 Model 2 Software Engineering n COCOMO Model Constructive Cost model Three model Model 1 Model 2 Mode 3

Software Engineering Model 1 is called Basic COCOMO n It has three level Organic Software Engineering Model 1 is called Basic COCOMO n It has three level Organic Semi-detached Embedded n

Software Engineering E= ab. KLOCbb n D= cb. Edd n N= E/D n Where Software Engineering E= ab. KLOCbb n D= cb. Edd n N= E/D n Where E is the development effort in PM and D is the development effort time in months and N is the no of people

Software Engineering n Make Buy decision: The software managers are often faced with the Software Engineering n Make Buy decision: The software managers are often faced with the problem of make buy decision. In some cases it is cost effective to acquire rather than internal development