Pune Ring Road • To avoid traffic congestion in the city it is necessary to have a ring road for Pune. • Decision taken in the meeting conducted by Hon’ble Chief Minister on 12/06/2007. • Pune and Pimpri – Chinchwad Municipal Corporation to make necessary provision in their Development Plan. • PWD to implement the project on BOT basis.
Ring road alignment • Survey of following stretches of ring road undertaken. • Part I – Theurphata NH 9, Kesnand, Wagholi, Bhavdi, Tulapur, Alandi, Kelgaon, Chimbli, NH 50. • Part II – NH 50, Chimbli Moi, Nighoje, Sangurde, Shelarwadi, Chandkhed, Pachne, Pimploli, Rihe, Ghotawde, Pirangutphat. • Part III – Pirangut, Bhugaon, Chandni Chowk, Ambegaon, Katraj. • Part IV – Ambegaon, Katraj, Mangdewadi, Wadachiwadi, Holkarwadi, Wadkinaka, Ramdara, Theurphata, NH 9
Proposed Ring road - Map
• Detail survey of Part I , II and IV completed. • Presentation was made on 19. 04. 2008. As Part III and IV are very close to the city limits considering rapid growth of city • Revised Alignment based on toposheets and google earth images for Part III & IV is considered.
Alignment Details Part I Theurphata NH 9, Kesnand, Wagholi, Bhavdi, Tulapur, Alandi, Kelgaon, Chimbli, NH 50. 39. 89 km Part II Chimboli phata to Nighoje to Sangurde, Shelarwadi, Shirgaon, Chandkhed, Pimploli, rihe, Ghotawde, Pirangutphat. 46. 40 km Part III Pirangut, Urwade, Mutha Bahuli, Sangrun, Nigde, Khamgaon, Ghera Sinhgad, Kalyan, Kondanpur, Shriramnagar 51. 20 km Part IV NH 4 , Gogalwadi, Patharwadi, Bhivri, Kanifnath, New Mula – Mutha canal, Theurphata, NH 9 32. 24 km After the alignment of Part III & IV is finalised detail survey work will be undertaken.
Acquisition Proposed • Ring road length 169. 73 km • Land Acquisition cost Rs. 2374. 00 crores • Construction cost Rs. 6065. 00 crores • Total cost Rs. 8439. 00 crores. • Satelite townships in 38. 38 km stretch in balance width of 200 m (expected area 8, 25, 93, 760 sq. ft) – by giving FSI of 1. 0 + additional 1. 0 = 2. 0 the expected revenue Rs. 9228. 00 crores.
Approx. estimates • Acquisition is proposed for 38. 38 km length – 300 m width, 121. 12 km length – 100 m width and 10. 44 km length – 45 to 60 m. • Acquisition cost - Rs. 2374 crores. • Construction cost – Rs. 6065 crores. • For the stretch of 38. 38 km road length acquisition is proposed for 300 m width and the width balance after that required for road i. e. 200 m will be developed with additional FSI of 1. 0 over and above existing 1. 0 FSI to make the project financially viable. • State Govt. to approve the project on a PPP model without toll alongwith concession of extra FSI.
Details of Ring road Name of the Road Length in m Flyovers Road Length in m Railway length in m Majo r bridg es lengt h in m Mino r bridg es lengt h in m Viadu cts bridg es lengt h in m Under pass length 8 9 Elevat ed road Land Acquisition 100 m width area in hectare s 300 m width road area in hectares 11 12 13 14 2750 355 132 3490 242. 6 695. 8 425 255. 00 1 2 3 4 5 6 7 1 ¦Part I – Theurphata, NH 9, Kesnand, Wagholi, Bhavdi, Tulapur, Alandi, Kelgaon, Chimbli, NH 50 39. 89 650 300 490 450 1260 2 ¦Part II – Chimboliphata to Nighoje to Sangurde, Shelarwadi, NH 4, Shirgaon, Chandkhed, Rihe, Ghotawde, Pirangut. 46. 400 160 200 850 300 630 3 Part III – Pirangut, Urwade, Mutha Bahuli, Sangrun, Nigde, Khamgaon, Ghera Sinhgad, Kalyan, Kondanpur, Shriramnagar. 51. 200 1850 1520 3070 90 2928 4 Part IV – NH 4, Gogalwadi, Patharwadi, Bhivri, Kanifnath, New Mula – Mutha canal, Theurphata, NH 9 32. 240 500 150 2250 980 8050 1200 203. 00 55. 70 45. 00 169. 940 3160 650 1200 5320 2960 11628 7440 1281. 4 1116. 8 2860 10 Tunnel s length in m 120 650