Скачать презентацию Reclaimed Arizona — Asphalt Pavement in Application and Скачать презентацию Reclaimed Arizona — Asphalt Pavement in Application and

54b5bad661288d9a7e1f5040e36732ff.ppt

  • Количество слайдов: 37

Reclaimed Arizona - Asphalt Pavement in Application and Verification October 3, 2008 Arizona Association Reclaimed Arizona - Asphalt Pavement in Application and Verification October 3, 2008 Arizona Association of County Engineers 1

Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Operations v Granite/ADOT Test Results v Summary 2

Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Operations v Granite/ADOT Test Results v Summary 3

Change in DOT’s 4 Change in DOT’s 4

5 5

Changing Market Conditions = Renewed Interest in Recycling v Price escalation for construction/rehabilitation and Changing Market Conditions = Renewed Interest in Recycling v Price escalation for construction/rehabilitation and maintenance v Asphalt binder shortages v Polymer shortages v Environmental concerns v Energy concerns v Funding limitations 6

States Allowance of RAP v 75 -percent of States allow at least 10 percent States Allowance of RAP v 75 -percent of States allow at least 10 percent RAP in surface course mixes v More States allow higher percentages in lower lifts 7

Value of Recycling – Percent Savings Relative to Conventional Materials – Initial Construction* 15% Value of Recycling – Percent Savings Relative to Conventional Materials – Initial Construction* 15% RAP in HMA 25% RAP in HMA 5 8 12 19 Aggregate Consumed, tons 6 10 CO 2 (lb) 7 12 CO (lb) 8 13 NOx (lb) 5 9 SOx (lb) 9 16 PM-10 (lb) 6 10 Energy, BTU AC Consumed, tons *equivalent square yards Note: Similar advantages found with Life Cycle Cost 8

PCI Over Time* *Projects constructed in Arizona 9 PCI Over Time* *Projects constructed in Arizona 9

Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Operations v Granite/ADOT Test Results v Summary 10

Project Layout 11 Project Layout 11

Standard Sections 12 Standard Sections 12

Scope of Work v Partial depth removal of existing asphalt concrete v Placement of Scope of Work v Partial depth removal of existing asphalt concrete v Placement of dense grade asphalt concrete v Placement of AR-ACFC v Miscellaneous other work v Granite’s Proposal v Use RAP in base course HMA v 6% coarse RAP (3/4 -in x 3/8 -in) v 9% fine RAP (3/8 -in minus) v Note: RAP currently used as shoulder backing and aggregate base on ADOT projects 13

Standard Section 14 Standard Section 14

Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Operations v Granite/ADOT Test Results v Summary 15

Alligator Cracking Moderate severity alligator cracking Existing pavement prior to rehabilitation 16 Alligator Cracking Moderate severity alligator cracking Existing pavement prior to rehabilitation 16

Transverse Cracking Slight to moderate severity transverse cracking Existing pavement prior to rehabilitation 17 Transverse Cracking Slight to moderate severity transverse cracking Existing pavement prior to rehabilitation 17

Block Cracking Block cracking Existing pavement prior to rehabilitation Maybe considered combination of longitudinal Block Cracking Block cracking Existing pavement prior to rehabilitation Maybe considered combination of longitudinal and transverse cracking 18

Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Operations v Granite/ADOT Test Results v Summary 19

Cold Milling Operations 20 Cold Milling Operations 20

Unprocessed RAP from I-19 21 Unprocessed RAP from I-19 21

Coarse RAP (3/4 -in x 3/8 -in) 22 Coarse RAP (3/4 -in x 3/8 -in) 22

Fine RAP (3/8 -in Minus) 23 Fine RAP (3/8 -in Minus) 23

Hot Plant Feeders 5 Virgin Aggregate Bins 2 RAP Bins 24 Hot Plant Feeders 5 Virgin Aggregate Bins 2 RAP Bins 24

Hot Plant Cement Silo and Pugmill Virgin Aggregate Scalping Screen 25 Hot Plant Cement Silo and Pugmill Virgin Aggregate Scalping Screen 25

Hot Plant Counter Flow Drum Mixer RAP Conveyor 26 Hot Plant Counter Flow Drum Mixer RAP Conveyor 26

Paving and Inspection HMA Paving Density Testing 27 Paving and Inspection HMA Paving Density Testing 27

Rolling Operations Echelon Breakdown Rolling Finish Rolling 28 Rolling Operations Echelon Breakdown Rolling Finish Rolling 28

Finished Mat 29 Finished Mat 29

Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Operations v Granite/ADOT Test Results v Summary 30

Granite Test Results – RAP* Testing Lab RAP Source Coarse Granite Arizona Fine No. Granite Test Results – RAP* Testing Lab RAP Source Coarse Granite Arizona Fine No. 200, % Passing Asphalt Binder Content, %DWA 10 10 10 2. 0 1. 1 0. 38 0. 53 11 11 11 0. 0 1. 9 1. 6 1. 17 1. 09 2. 81 0. 94 0. 28 Stat 3/8 -in Sieve, % Passing No. 8 Sieve, % Passing No. 40 Sieve, % Passing No. 10 10 Std. Dev. ** 3. 5 No. Std. Dev. Granley Std. Dev. Rep. Range Std. Dev. 2. 0 – 4. 5 2. 0 – 3. 5 0. 5 – 1. 5 0. 15 – 0. 45 Rep. Value Std. Dev. 3. 30 2. 80 0. 90 0. 30 *Test results based on ignition oven **Standard Deviation – measure of variability 31

Granite Test Results – RAP* Testing Lab RAP Source Coarse Granite Arizona Fine No. Granite Test Results – RAP* Testing Lab RAP Source Coarse Granite Arizona Fine No. 200, % Passing Asphalt Binder Content, %DWA 5 5 5 3. 2 1. 5 0. 60 0. 42 7 7 7 0. 0 1. 9 1. 1 0. 70 0. 22 2. 81 0. 94 0. 28 Stat 3/8 -in Sieve, % Passing No. 8 Sieve, % Passing No. 40 Sieve, % Passing No. 5 5 Std. Dev. ** 5. 3 No. Std. Dev. Granley Std. Dev. Rep. Range Std. Dev. 2. 0 – 4. 5 2. 0 – 3. 5 0. 5 – 1. 5 0. 15 – 0. 45 Rep. Value Std. Dev. 3. 30 2. 80 0. 90 0. 30 *Test results based on solvent extraction **Standard Deviation – measure of variability 32

Granite/ADOT Test Results - Gradation v Gradation of aggregate extracted from field mixed samples Granite/ADOT Test Results - Gradation v Gradation of aggregate extracted from field mixed samples Standard Deviation of Percent Passing Sieve, % 3/8 -in No. 8 No. 40 No. 200 Granite 2. 95 2. 56 1. 18 0. 57 ADOT 3. 22 2. 14 0. 88 0. 46 Granite & ADOT 3. 10 2. 35 1. 04 0. 51 Granley NCHRP 455 2. 81 0. 94 Rep. Range 2. 0 – 4. 5 2. 0 – 3. 5 0. 5 – 1. 5 Rep. Value 3. 3 2. 8 0. 9 *Standard Deviation – measure of variability 33

Granite/ADOT Test Results - Volumetrics v Volumetric properties of field mixed/lab compacted samples Bulk Granite/ADOT Test Results - Volumetrics v Volumetric properties of field mixed/lab compacted samples Bulk Density, lb/ft 3 Rice Air Asphalt Density, Voids, % Binder lb/ft 3 Content, % Granite 0. 95 0. 58 0. 81 0. 29 ADOT 0. 80 0. 49 0. 67 0. 21 Granite & ADOT 0. 88 0. 53 0. 74 0. 25 Granley NCHRP 455 0. 28 Rep. Range 0. 3 – 1. 2 0. 15 – 0. 45 Rep. Value 0. 7 0. 3 *Standard Deviation – measure of variability 34

Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Outline v Introduction v Project Overview v Existing Pavement Condition v Construction and Production Operations v Granite/ADOT Test Results v Summary 35

Recycling Benefits v Conservation v Materials (aggregate and asphalt binder) v Energy (burner fuel, Recycling Benefits v Conservation v Materials (aggregate and asphalt binder) v Energy (burner fuel, trucking, etc. ) v Preservation of environment v Landfill v Green house gases (global warming) v Sustainability v Economics v Reduce first and life cycle cost v Complete reconstruction vs. alternative methods v Increased contractor competition 36

Questions 37 Questions 37