Скачать презентацию Project implementation changes reporting Edmunds Sniķeris Edmunds Snikeris latlit Скачать презентацию Project implementation changes reporting Edmunds Sniķeris Edmunds Snikeris latlit

586276439b9f9ead86b611efb517ba4e.ppt

  • Количество слайдов: 17

Project implementation, changes, reporting Edmunds Sniķeris Edmunds. Snikeris@latlit. eu Joint Technical Secretariat 16 April Project implementation, changes, reporting Edmunds Sniķeris Edmunds. Snikeris@latlit. eu Joint Technical Secretariat 16 April 2012, Kuldīga

Project Implementation Key aspects: Application Form Feasibility Study Cost estimations Technical Project = Project Project Implementation Key aspects: Application Form Feasibility Study Cost estimations Technical Project = Project results Specifications of equipment Project monitoring and control 2

Monitoring Programme level Progress reports every 6 months, Project visits by the JTS, construction Monitoring Programme level Progress reports every 6 months, Project visits by the JTS, construction experts Project Level Constantly by the Lead Partner/periodically by the Steering Group 3

Changes in projects Minor deviations that are not considered as Project changes: Changes in Changes in projects Minor deviations that are not considered as Project changes: Changes in contact info, minor rescheduling, deviations from the spending targets, small deviations from specifications, changes between the costs of items within one budget line and work package. Can be reported as „deviations‟ to the JTS through the Progress Report Project have to make changes: 1. Project Partnership; 2. Budget Reallocation; 3. Project Activities and Outputs; Request for changes procedure - www. latlit. eu, section “How to Implement” 4. Modification of the Duration of the reporting Period; 5. Prolongation of the Project Duration. 4

Budget rellocation Requirements: ´ reallocation must be justified; ´ cannot request to increase the Budget rellocation Requirements: ´ reallocation must be justified; ´ cannot request to increase the ERDF co-financing; ´ foster more efficient achievement of project objectives and results; ´ the project can reallocate the budget between the BLs and/or work packages up to 30% of the total eligible project budget; ´ as an exception, changes exceeding 30% reallocation between BLs/work packages are to be considered by the JMSC. As a rule, the budget reallocation can be requested only once during the project implementation. Only in well justified cases, the project can apply for subsequent budget reallocation. 5

Project Activities and Outputs Following cases are possible: ´ increase/decrease amount of the existing Project Activities and Outputs Following cases are possible: ´ increase/decrease amount of the existing project output, extension/reduction of range of the existing activity (considerable change of the project output/activity that was initially planned in the project application); ´ creation of a new project output and/or activity (inclusion of new output and/or activity that was not previously planned in the project application). 6

Project Changes Procedure It is strongly recommended to consult with the JTS before submitting Project Changes Procedure It is strongly recommended to consult with the JTS before submitting request for changes! 1. LP sends electronic version of the request for changes, AF, FS, technical documents, budget reallocation to the JTS 2. Harmonization of documents 3. LP sends paper version of harmonized documents 4. Decision taking process: JMSC, MA, JTS 5. Notification Letter to the LP 6. If changes are approved – LP sends updated Application Form and Feasibility Study 7. Addendum of Subsidy Contract is signed 7

Construction works Construction works

Information to the JTS According to the Subsidy Contract (Paragraph 5; Point 6. 18. Information to the JTS According to the Subsidy Contract (Paragraph 5; Point 6. 18. ) Lead Partner is responsbile for submission of all the PPs’ calendars for the planned construction/renovation works to the responsible project manager of the JTS within 2 weeks after the contract on construction/renovation works is signed by including: 1. the start date of the works; 2. location; 3. deadlines; 4. Indicative payment plan. 9

Changes in construction works - 1 1. Small deviations from the works and amounts Changes in construction works - 1 1. Small deviations from the works and amounts planned in the technical documentation as sub-items in the cost estimation for planned (re)construction works could be eligible if total amount for works does not exceed the planned in the project application: ´LP/PP prepares acts on changes; ´Submits acts to the first level controller; ´in case there any doubts if it is small deviation or additional (re)construction works JTS could be contacted for exhaustive explanation. 10

Changes in construction works - 2 2. Unexpected works: ´During the (re)construction works, unexpected Changes in construction works - 2 2. Unexpected works: ´During the (re)construction works, unexpected works are possible and such works are being evaluated by controllers on case by case bases (could be harmonised as deviations); ´Acts, where justification of changes is described, should be submitted by PPs to controllers. 3. Additional works → If additional works have to be implemented by the project partners, LP shall submit Request for Changes in accordance with existing procedure (http: //www. latlit. eu/eng/how_to_implement/project_changes). 11

Reporting Procedure ´ Six-months Reporting Periods (RP): ´ 1 November – 30 April ´ Reporting Procedure ´ Six-months Reporting Periods (RP): ´ 1 November – 30 April ´ 1 May – 31 October ´ PP sends to the FLC Partner Reports: 10 days after the end of the RP ´ LP submits filled Progress Report to the FLC 2 weeks (latest) before deadline for submission to the JTS ´ In 3 months after the end of the RP the LP submits Progress Report to the JTS 12

Reporting Procedure 13 Reporting Procedure 13

Reporting/ Payment Procedure JTS Within 3 months after the end of Reporting Period Lead Reporting/ Payment Procedure JTS Within 3 months after the end of Reporting Period Lead Partner Pre-filled Reporting Form Progress Report 70% payment, if 1 st check of PR is passed PP 1 PP 2 PP 3 Max period for check & clarification 6 months after submission Full check of PR Preparation of payment Clarification Answers Payment CA 14

Forms: ´ JTS sends out a pre-filled Progress Report form to LP ´ Partner Forms: ´ JTS sends out a pre-filled Progress Report form to LP ´ Partner report, timesheet, list of participants form available as attachment to FLC guidelines 15

Reporting LP sends the following documents to the JTS: ´ ´ Original Certificate of Reporting LP sends the following documents to the JTS: ´ ´ Original Certificate of Proficiency of the LP Controller Copies of Confirmations of all the PP’s controllers Verified Progress Report: ´ ´ ´ Signed by LP and FLC In electronic and paper version In English language Information provided in the PR should be comparable with information provided in the AF. 16

Reporting LP sends the following supporting documents to the JTS: ´ Events documents (e. Reporting LP sends the following supporting documents to the JTS: ´ Events documents (e. g. agenda, list of participants with signatures for each day, photos, see full list in PM, 10. 1. 2) ´ Copies of outputs produced (e. g. studies, press articles, leaflets, pictures of infrastructure, recordings of TV or radio broadcasts, etc. ) 17