PRESENTATION ON FIRE AND GAS SYSTEM By Satish Makwana - Instrument Department Date : 04/05/2012
Why F&G System is required ? Big fire in IOC depot near Jaipur PROPERTY - Loss 350 + Cr. Deaths 12 - Loss ? .
F&G System at Mangala F&G - MPT FIELD F&G BUILDING F&G Fire Station CCB/Ch. Lab/SS 5 SS 1 A SS 1 B SS 2 VRU SS 3 Export Oil SS 4 A Diesel Tank/Flare SS 4 B Warehouse Train # 2 Train # 3 Train # 4 GPA F&G - WELLPAD FIELD F&G All Cellar pits in Wellpad #1 TO 18 BUILDING F&G Wellpad #1 TO 18
When Alarm comes what we have to do first? Identify Field or Building F&G Alarm? At Control Room At Fire Station Check Building Fire Monitoring Stations Check Field F&G Station Overview Identify the Area having Alarm Silence the Alarm Inspect the area find the abnormality Do suitable action for rectification Normalize the system by reset Contact Fire Station for Building F&G
Field F&G Alarms Ø Any of the Flame detectors, Point gas detectors, Open path detectors or Deluge valves operated will generate alarm. Ø Any manual call points if Glass is broken will generate alarm. Ø Any alarm generated will be highlighted on the operator screen and the corresponding zone will become red.
Field F&G Trips Ø Two no. of alarm generated in one Zone will be considered as a confirmed fire or gas presence in the zone and will result an alarm and process shutdown (PSD-2) for the particular zone. Ø Confirmed fire or gas alarm in two Zones will result in ESD 1 and PAGA (Public address and general alarm system). Ø All the process and power except UPS power will trip.
Is Our Building F&G System Reliable?
Is Our Build F&G System Reliable? Date Description Action Taken 3 -Feb-12 SS-1 A PANEL ROOM MPT-SD-817145 M 1 -145 Activated due to STG 970 LAPT Failure 3 -Feb-12 SS-1 A PANEL ROOM MPT-SD-817114 M 1 -114 Activated due to STG 970 LAPT Failure 3 -Feb-12 SS-1 A PANEL ROOM MPT-MSD-817113 M 1 -113 Activated due to STG 970 LAPT Failure 12 -Apr-12 SS 4 BBATT RM DET ACT/MPT-ZAM-81709/M 1 -109 Heat detector cleaned 12 -Apr-12 CHEMICAL BUILDING MPT-ZAM-817107 -M 3 -107 Due to drilling dust generated alarm 21 -Apr-12 SS 2/PANEL EQUIP/MPT-SD-81740/SMOKE DET No information 21 -Apr-12 CHEMICAL BUILDING MPT-ZAM-817108 -M 3 -108 Fault Heat detector Replaced
Is Our Field F&G System Reliable? 4000 Field F&G Status from 11 -04 -2012 to 02 -05 -2012 3500 3000 2500 2000 Series 1 3733 1500 2159 1000 500 972 515 0 Override Activity IOP PSH ALM HHH
Workout Done by F&G Team after commissioning ØCleaned and Serviced the detectors to avoid Frequent False alarm coming due to dust (by construction activity) ØNRV installed in Deluge circuit to avoid False operation of other Deluge valves due to high DP across them ØHVAC interlocks taken in line ØInergen system made ready (still in Manual) ØField F&G interlocks lined up ØThe Well pad Building F&G Alarm connected to our F&G CCB ØFire station HMI Installed for monitoring Field F&G Ø ESD- 1 taken in line with all relevant more than 35 F & G Tags which were in bypassed condition earlier ØWe have already reduced the AMC cost 50% by taking the building F&G PM jobs.
Field F&G Instrumentation IR 3 Flame Detector - 48 Open Path Gas Detector OR Line of Sight Gas Detector -12 Point Gas Detector – 6 Deluge Valve – 23 Manual Call Point – 107
Location of Field F & G Instruments Ø Train-2 8 FD , 3 Open path Gas Detector Ø Train-3 8 FD , 3 Open path Gas Detector Ø Train-4 14 FD , 3 Open path Gas Detector Ø VRU 6 FD , 6 Point Gas Detector Ø Export oil tank 4 FD Ø Diesel tank / Flare area 6 FD Ø GPA area 2 FD , 3 Open path Gas Detector
IR Flame Detector Make : Sharp eye Model no: 20/20 SI The principle of flame detector is based on the detection of IR radiation from the flame and Flame detector will gives Analog output signal to the system. The system will generate an alarm based on the intensity of IR rays
Open Path Gas Detector Open path Gas Detector OR Line of sight Gas Detector Make : Spectrex Inc. – Saf. Eye Model : Source - OPS-FI 3 SE Model : Detector - OP-IF 100 SE Source Detector The principle of open path gas detector is based on the absorption of radiation ( IR rays ) caused by the presence of Gases in the medium and the losses of the transmitted IR spectrum is sensed by the Detector.
Point Gas detector Ø Make : Crocown Ø Model : Nimbus is a fixed point infrared gas detector for the detection of common hydrocarbon gases in the range 0 -100% LEL and provides a 4 -20 m. A signal proportional to the Gas concentration.
Deluge Valve Ø Deluge valve Ø Make : Darling Muesco
LINE DIGRAM FOR DELUGE SYSTEM SOV Manual Drain Needle Valve PSL NRV QB Loop PSH Fire water I/L line Deluge valve Equipment to be protected
WORKING PRINCIPLE and OPERATION Ø Deluge valves are held shut with pressurized water placed in the valve’s priming chamber. Release of water pressure by any of the below mentioned ways from priming chamber will operate deluge valve Ø Ø If the Detection line pressure decreases due to QB rupture Manual Operation from Field Manual Command from DCS Auto Operation Due to Confirmed Fire or Gas Alarm
Manual Call Point Ø Make : MEDC
Building F&G Instrumentation Ø Conventional type smoke/Heat Detectors Ø Smoke detectors -addressable Ø Open Path Beam smoke Detectors -addressable
Smoke and Heat detectors Ø Smoke detectors Ø Make : TYCO Ø Model no. - 4098 -9714
Conventional type smoke/Heat detectors MAKE : TYCO MODEL NO : MR 601 TEX CONVENTIONAL TYPE SMOKE/HEAT DETECTOR
Cairn India – 2007 Beam Detector Ø Make : TYCO Ø Model no : simplex fire ray 50 ru
DGFAP (Data Gathering Fire Alarm panel) Make : Simplex Building Smoke / Heat Detector are connect in DGFAP All Building DGFAP are connect in network loop
DGFAP (Data Gathering Fire Alarm panel) DGFAP Alarms Trouble Alarm Fire alarm All Building DGFAP Connect in ID Net Loop as below Fire station – CCB – SS 1 A – SS 1 B – SS 2 – SS 3 – SS 4 A – SS 4 B- SS 5 – Ware house-Fire station
Our Future Focus Ø One Building F&G Monitoring Station to be installed in CCR Ø All Wellpad building F&G system to be hooked up with our MPT Fire Station through FO and finally to ID net Ø Fire Station , Warehouse , Security Building , Wellpads Graphics to be incorporated. Ø Fire Station and Security building and Wellpads to be configured for alarm History Ø Train # 2 , Train # 3 Beacon alarm incorporation Ø Boiler and STG Area Fire and Gas system Installation and Commissioning
ANY QUESTION? ?