Performance Management Presentation ORF Manage Policy and Program Assessment for the Delivery of NIH Owned and Leased Facilities Team Members: Division of Policy and Program Assessment Farhad Memarzadeh, Sheri Bernstein, Reza Jafari, Robert Henry, Mike Shaw & Clarence Dukes 14 January 2005 1
Overview and Contents ORF • • Background on DPPA Our Mission? What Services We Provide? Who Do We Serve? Who Are Our Stakeholders? What Is Critical for Our Success? What We Have Learned? What Our Customers Think About the Services We Provide? • Our Next Steps? 2
Background on DPPA ORF • Resulted from 2002 re-alignment of the Office of Research Services. • In operations > 2 years. • Consist of Policy and Quality Assessment Branches. • Strive to provide tools to streamline and improve delivery of NIH real property. • FY 04 is the Baseline Assessment Year for measuring performance. 3
Our Mission ORF To responsibly execute the public trust by management and development of policies and procedures to help achieve the best value and quality at all levels of project design, construction, commissioning and operations within the Office of Research Facilities (ORF) 4
ORF 5
What Services We Provide? (DS = Discrete Services) ORF • DS # 1: Provide policies, standards & guidelines for NIH owned & leased facilities. • DS # 2: Ensure ORF operations conform to applicable regulations, codes, standards and guidelines. • DS # 3: Develop suitable performance management methods to evaluate, improve and enhance delivery of facilities. • DS # 4: Coordinate training to maintain technical excellence and support effective implementation of policies and procedures. • DS # 5: Prepare the facilities section of the NIH Government Performance and Results Act (GPRA) Plan. 6
Who Do We Serve? ORF • Our Customers – – – Project Officers Program Managers Facility Managers Branch Managers Division Heads • Our Stakeholders – Architects-Engineers – National Center for Research Resources – Colleges, universities, state & local governments involved with the design & construction of facilities using grant funds 7
ORF What Is Critical for Our Success (FY 04 Objectives) • Adopted a Strategy Mapping Approach – Focused on activities that directly contribute to successful accomplishment of long term objectives. • Those that benefit 1 st Line customers (Program Managers & Project Officers). – Be consistent with the Performance Management Plan (PMP) methodology – Evaluate & Assess Critical Performance Measures linked to the Customer, Internal Business, Learning & Growth & Financial Perspectives that are part of the balanced scoreboard. • FY 04 is the baseline year for analysis of our performance. – Focus on determining how well services are being delivered in providing the expertise, practices, tools and guidance to help Project Officers monitor & measure 8 project status.
What Is Critical for Our Success (FY 04 Critical Measures) ORF • From the Customers Perspective – – % Project Review Board (PRB) reviews that meet due dates # Customers attending training • From an Internal Business Process Perspective – # Qualified Projects using Earned Value Analysis (EVA) • From a Learning and Growth Perspective – Training hours related to EVM and related professional development • From a Financial Perspective – Unit cost of Discrete Services 9
ORF Customer Perspective Critical Measures 10
Objective C 2. Improve availability and reliability of guidance and expertise ORF Measure: C 2. a. % PRB’s Reviews that meet due dates Percent Month 11
Objective C 3. Our customers are familiar with the Guidelines ORF Measure: C 3. a. % Scheduled customers attending training • Design Policy & Guidelines (DPG) training was only offered in the 2 nd Qtr of FY 04 • 172 people attended, this included: – ORF participants – ICD participants – Architect-Engineering Firms • Approximately 85% of ORF has received DPG training 12
ORF Lessons-learned from Customer data? Data Analysis indicated: • Our Customer Base must be verified. • Customer Surveys must be analyzed when a minimum response rate of 25% is received. • Use of Customer Surveys must be expanded. • Training in the PMP will benefit customers/clients for a full understanding of the linkage between: ü The NIH Strategic Plan ü DHHS Goals & Objectives ü OMB & the presidents Management Objectives 13
ORF Actions taken Based on Customer data? Data Analysis indicated several possible conditions: • Additional Customer Surveys have been developed & distributed. • Customer Surveys have been tailored to fit the requirement. • Training to address core business practices is being discussed. • Looking at the use of Focus Groups for feedback. • We are re-evaluating our Customer & Stakeholder base. 14
ORF Internal Business Perspective Critical Measures 15
ORF Objective: IB 1. Improve thoroughness, reliability & accuracy of policies, guidelines, standards & procedures Measure: IB 1. e # of Project Reviews completed on schedule Number of Projects FY 04 Quarter 16
Objective: IB 2. Improve Best Value Analysis Measure: IB 2. a # of Qualified projects using EVA ORF Number of Projects FY 04 Quarter 17
ORF SAMPLE S-CURVE TRACKING SCHEDULED VS ACTUAL EXECUTION GOALS 18
ORF NCRR Technical Grant Review (Workload Summary) • 151 Submittals received for review • Workload Reflects • 66 – Final Contract Documents approved • 70 – Active Grants & end of FY 04 # of Projects – 25 Colleges & Universities – 8 Institutions – 1 Historically Black College/University FY 04 Quarter 19
Lessons-learn from Internal Business Process (IBP) data? ORF • Our automated management system must be modified to provide user friendly reports on project reviews. • Additional EVMS training is required. • Need to improve the EVMS contract clause & enforcement for performance of EVMS. • Additional Resources are required to handle the PRB workload. • Databases Used for project reporting must be fully populated to permit accurate assessment of performance & accomplishments. • Monthly management reports are essential to our success. • Our Grant Program workload must be highlighted. • Time required for project reviews must be re-evaluated. 20
Actions taken Based on IBP data? ORF • More analysis of our project review process would be beneficial. • Additional training in our core business practices is being facilitated to assure they are fully understood to facilitate adopting a a day to ay practice. • Recommending use of team building for program performance enhancements. This could be a cross-organization initiative. • Facilitating including additional management tools for project reporting • Educate the NIH Community & staff on services provided & how they enhance performance and delivery of facilities. • Standardize business practices to help ensure continuous delivery of quality products, services and facilities. 21
ORF Learning & Growth Perspective Critical Measures 22
ORF Objective L 1. Be experts in best practices for project analysis and quality assurance Measure L 1. a: Customer Survey FY 04 Quarter 23
Objective L 1. Be experts in best practices for project analysis and quality assurance ORF Measure L 1. b: Training hours for assessment and interpretation of EVM and related professional development courses FY 04 Quarter 24
Earned Value Training Survey Summary ORF q Number of Students 30 q Number Man-hours 240 q Student Breakdown ü ü ü Program Managers Project Officers Contracting Officer Contract Specialist Contractor Number of Respondents q Response Rate q Maximum Possible Score q Average Score 5 10 2 1 1 19 63 % 10 7. 93 25
Earned Value Training Summary How would you rate the following? ORF ( 1= Unsatisfactory to 10 = Outstanding ) 26
Earned Value Training Summary Instructor and Training Material Rating ORF ( 1= Unsatisfactory to 10 = Outstanding ) 27
ORF Earned Value Training Conclusions From Findings • Satisfaction was highest with: – The Instructor as a subject matter expert. – Quality of Training Materials – Answered my questions regarding what earned value is. – Answered my questions regarding benefits of earned value – Answered my questions regarding what are earned value indices and triggers that let you know you have a problem • Satisfaction was lowest with: – Answered my questions regarding difference between earned value and other project management processes – Answered my questions regarding whether earned value can be used for various contract acquisition types – Answered my questions regarding why earned value is needed • Comments indicate: – Course length must be re-evaluated. – Colors used in training material to be re-evaluated. – Contractors must be brought up to speed on EVMS requirements. 28
How would you rate the following? ( 1= Poor to 5 = Excellent ) Pre-project Planning ORF 29
ORF Pre-Project Planning Training Survey Summary q January 12 -13, 2004 – Atlanta – # Surveys Distributed 31 – # Respondents 23 – Response Rate 74% q February 3 -4, 2004 – Rockville – # Surveys Distributed 35 – # Respondents 28 – Response Rate 80% q February 17 -18, 2004 – Bethesda – # Surveys Distributed 35 – # Respondents 26 – Response Rate 74% 30
Redi-Check Training & Survey Summary ORF q No. of Students 36 q Student Breakdown ü ü ü Program Managers Project Officers Contracting Officer Others # of Respondents q Response Rate q Maximum Score q Average Score 5 10 2 4 18 50 % 10 8. 95 31
ORF Lessons-learned from Internal Learning & Growth (L&G) data? • Education of the PMP Process and its relationship to Individual Development or Performance Plans (IDP) is essential. • IDP are recommended for all that are linked to the PMP and other management objectives based on the position. • Budgeting for training should be linked to IDPs. 32
Actions taken Based on L&G data? ORF • Training required in the following areas: • EVMS • PDRI • Design-Build • Appropriation Law • Cost Estimating • Team Building • Project Risk Management • An Organization Training Development Plan should be developed as employee orientation guide & expand for ORF). 33
Financial Perspective ORF Critical Measures 34
HOURS BY COST ACCOUNT ORF 35
BILLABLE HOURS BY COST ACCOUNT ORF 36
SALARY BY COST ACCOUNT ORF 37
Objective F 1. Minimize unit costs ORF Measure F 1. 1 Comparison Year to Year Discrete Service Costs 38
Lessons-learned from Financial data? ORF • Our Timecard Module must be expanded to capture reports needed for fiscal management. • Cost reporting must be enhanced to capture all cost associated with the services provided. • Resources allocation should be re-analyzed after the ORF realignment is completed. • Actual to budget comparisons should be fully supported to enhance planning for the future. • Monthly management reports should be generated to evaluate how resources are being utilized. 39
ORF Actions taken Based on Financial data? • Validating cost of Discrete Services. • Facilitating additional management reports. • Resources can be shared based on data from monthly workload summaries. • Discussing budget formulation and issues. • Starting cost trending analyses. 40
Conclusions ORF Need to continue analysis of how we use/allocate professional resources in performing our Discrete Services. Key FY 05 Initiatives: Training Policy Development Design-Build Portfolio Management Pre-Project Planning (PDRI) Post Occupancy Evaluation Design Policy & Guidelines Building Occupancy EVMS Security Permitting Process Other Actions Quality System Manual Develop New Employees orientation plan New A/E Selection Form Develop employee training plan Appropriation Law Enhance Quality Assessment of facilities 41