bbb5823de7b503a0886a2500388f39c0.ppt
- Количество слайдов: 42
Office of Innovations and Solution ACB-1 Project Management Principles and Practice for Managers Presented by: Pat A. Eigbe, PMP® Office of Innovations and Solutions, ATO-P February 17, 2004 Pat A. Eigbe, PMP®
Briefing Outline Q Project Management (PM) as a Tool Q Project Management Terminology Q PM Relationship to other Disciplines Q Project Management Processes Q Project Management Tools & Techniques Q Summary/Conclusion Q Questions February 17, 2004 Pat A. Eigbe, PMP® 2
Project Management as a Tool Q Minimize Fire Drills Q Efficient Use of Resources Q Develop Better Metrics Q On-time and On-budget Product Delivery Q Apply Lessons Learned Q Better Communications Between Stakeholders Q Make Proactive Decisions February 17, 2004 Pat A. Eigbe, PMP® 3
Project Management (PM) Terms Q Project - A temporary endeavor undertaken to create a unique product or service. a ATOP or VSCS - Project has a specific purpose with a start and an end date. Q Project Management - the Application of Knowledge, Skills, Tools, and Techniques to Project Activities to Meet Project Requirements. February 17, 2004 Pat A. Eigbe, PMP® 4
Project Management Terms II Q Program - A group of related projects managed in a coordinated way. Programs usually include an element of ongoing activity. CPDLC, SMA, URET CCLD, p. FAST, as FFP 1 a PM Tools Development as part of Program Management a QA Project/Program Manager (PM) - The Individual Responsible for Managing a Project/Program. February 17, 2004 Pat A. Eigbe, PMP® 5
Project Management Terms III Q Work Breakdown Structure (WBS) “A deliverable-oriented grouping of project elements that organizes and defines the total scope of the project. Each descending level represents an increasingly detailed definition of a project work. February 17, 2004 Pat A. Eigbe, PMP® 6
Project Management Terms IV Q FAA standard wbs 1 -0. ppt Q WBS Dictionary 3. 1 Q Requirement to use FAA Standard WBS – Mandatory February 17, 2004 Pat A. Eigbe, PMP® 7
Project Management Terms V Q Q Q Deliverable – Tangible, verifiable work product or service. Work Package – A deliverable at the lowest level of the work breakdown structure. A work package may be divided into activities. Activity - Work elements with expected duration, cost, & resources that may be subdivided into tasks. February 17, 2004 Pat A. Eigbe, PMP® 8
Project Management Terms – VI Q Stakeholder – Individuals or Organizations that will be Impacted by the Outcome of a Project. Q OBS: An Organizational Chart Relating Work Packages to Organization Units. Q Responsibility Matrix: Relates Organization Structure to WBS & Ensures that each Element of the Project’s Scope is Assigned to a Responsible Individual(s). February 17, 2004 Pat A. Eigbe, PMP® 9
Project Management: Relationship to Others Disciplines The PMBOK™ Project Management Knowledge and Practice General Management Knowledge and Practice Application Area Knowledge and Practice Figure is conceptual and overlaps are NOT proportional February 17, 2004 Pat A. Eigbe, PMP® 10
Systems Engineering/PM Relationship – I Q PM Needs SE for Integrated PM System Design a Requirements for HW and SW Tools a Q SE Needs PM for Planning and tracking a Managing Resources a Q PM System Designer Must Understand both Q SE Not Necessary for PM Practitioners February 17, 2004 Pat A. Eigbe, PMP® 11
Systems Engineering/PM Relationship - II Q Risk Management PM - Schedule, Cost & Technical/Quality a SE – Compatibility of Components of a System or Sub-System a Q Quality Management PM - Process for Producing the Product a SE - Ensure Product Meets the Quality Specifications a February 17, 2004 Pat A. Eigbe, PMP® 12
Systems Engineering/PM Relationship - III Q Configuration Management PM - Ensure Integrity of Schedule and System for Schedule Management a SE - Ensure Integrity of the System as Designed a Q Change Management PM - Changes to Project Scope a SE - Changes to System Requirement a Q Measurement PM – Program cost & schedule performance a SE – Technical Performance a February 17, 2004 Pat A. Eigbe, PMP® 13
PMI Certification Q What is PMP® Q What PMP® is not Q PMP® Value to Holder & Employer Q PMP® Certification Process link – visit Q http: //pm. act. faa. gov February 17, 2004 Pat A. Eigbe, PMP® 14
PM Process Groups Project Information Flow Initiating Processes Planning Processes Executing Processes Control Processes Closing Processes February 17, 2004 Pat A. Eigbe, PMP® 15
PM Process Flow February 17, 2004 Pat A. Eigbe, PMP® 16
Initiation Processes Q Q Q Identify project and sponsor Appoint Project Manager Train team on Project Management Process a Project Plan (PMIP) a Q Develop Program Directive to Include WBS that Covers the Scope a High-level Milestones a Budget resources a February 17, 2004 Pat A. Eigbe, PMP® 17
Planning Processes I Q Identify Life Cycle approach Evolutionary (AMS 6101, Section 2. 2) a Incremental a Waterfall a Q Risk Management plan February 17, 2004 Pat A. Eigbe, PMP® 18
Planning Processes II Q Get approval for Program Directive Q Identify quality standards - use specs, IEEE, ISO, PMBOK® Q Organizational structure Q Communications - who needs, what Q Acquire human resources for projects February 17, 2004 Pat A. Eigbe, PMP® 19
Planning Processes III (Schedule Development) Q Update & Decompose WBS Q Identify activities Q Sequence Q Estimate duration Q Estimate cost Q Allocate resources to work packages Q Baseline schedule February 17, 2004 Pat A. Eigbe, PMP® 20
Planning Processes IV Q Risk management detail: Identification a Analysis a Response a Procurement a February 17, 2004 Pat A. Eigbe, PMP® 21
Implementation/Execution Processes Q Use the PMIP to execute project activities Q Assess Technical Performance to assure product acceptance Q Distribute project information Q Make purchases Q Develop team skills/competencies Q Develop a Change Management plan February 17, 2004 Pat A. Eigbe, PMP® 22
Performance Measurement Tools Q Variances Q Performance Indices Schedule performance Index (SPI) a Cost performance Index (CPI) a Q Earned Value Management System (EVMS) February 17, 2004 Pat A. Eigbe, PMP® 23
Earned Value Management System Highlights Q What is EVMS Q Planning for EVMS Q Tracking & Analysis Q Elements of EV Analysis Q Project Cost & Schedule Forecasting Q EV Reporting February 17, 2004 Pat A. Eigbe, PMP® 24
Earned Value Management System (EVMS) - I Q EV - Tool for Measuring Project Performance Q Integrates Cost, Scope & Schedule measurements Q Compares work actually accomplished to work planned Q EV is an Early Warning System Q Helps management make proactive decisions to keep projects on course February 17, 2004 Pat A. Eigbe, PMP® 25
Earned Value Management System (EVMS) - II Q Involves Calculating 3 key Elements Budget - BCWS a Actual Cost - ACWP a Earned Value/Physical Progress - BCWP a Q Basis for variance analysis February 17, 2004 Pat A. Eigbe, PMP® 26
Planning for EVMS - I Q Create a work breakdown structure Q Organize work into discrete work packages and activities Q Allocate a budget to each of the activities Q Develop a schedule and Assign resources Q Must include all project work in the schedule Q Establish the Project Baseline February 17, 2004 Pat A. Eigbe, PMP® 27
Planning for EVMS - II Q Award performance credit for physical % complete: Q 0 -100 Short duration tasks < 160 hours a EV is Zero until activity is complete a Q 50 -100 Duration less than 600 hours a 50% at start of activity & 50% at completion a February 17, 2004 Pat A. Eigbe, PMP® 28
Planning for EVMS - III Q Interim milestone; Duration less than 600 hours a Based on completed milestone for task a Q Level of Effort (LOE) Long duration & consistent tasks a Difficult to measure - no tangible deliverables a Measured by duration of time used e. g. 10 weeks support is 50% complete at 5 weeks a February 17, 2004 Pat A. Eigbe, PMP® 29
Tracking & Analysis Q Each update cycle/Reporting Period: Obtain physical % complete for each task a Calculate EV for each task a Sum up EV for all tasks as project EV a Calculate actual expenditure for actual work completed during the period a Compare the Cumulative EV to Actual expenditure a February 17, 2004 Pat A. Eigbe, PMP® 30
Elements of EV Analysis - I Q Performance indices relate value of work performed to dollar spent. e. g. CPI = 0. 65 means that for every dollar spent, actual value of the work performed is $0. 65. Q Cumulative CPI used to forecast project cost at completion Q Cumulative SPI used to forecast project completion date February 17, 2004 Pat A. Eigbe, PMP® 31
Elements of EV Analysis - II Q Cost Variance - Difference between budgeted cost of an activity & actual cost of that activity a CV = EV - ACWP Q Schedule Variance - Difference between scheduled completion & actual completion of an activity a SV = EV - BCWS February 17, 2004 Pat A. Eigbe, PMP® 32
Elements of EV Analysis - III Q SPI – EV/Planned Value Q SPI => 1. 0, Project Schedule performing as planned or better Q SPI < 1. 0, Project not performing as planned - needs help February 17, 2004 Pat A. Eigbe, PMP® 33
Elements of EV Analysis - IV Q CPI – EV/Actual Cost Q CPI => 1. 0, Project Cost performing as planned or better Q CPI < 1. 0, Project Cost not performing as planned - needs help Q % Over/Under Budget = CAC - BCWS February 17, 2004 Pat A. Eigbe, PMP® 34
Project Cost & Schedule Forecast Methods Q Estimate at Completion (EAC) is total cost to complete an activity, work package, or a project expressed as: a EAC = Actuals-to-date + Estimate to complete (ETC) Q Cost EAC = BAC/CPI February 17, 2004 Pat A. Eigbe, PMP® 35
EV Reporting Q Interpret the output of EV calculations Q Take corrective action as necessary Q Recommend or take corrective action as necessary February 17, 2004 Pat A. Eigbe, PMP® 36
Control Processes I Q Coordinate and control changes to project scope/requirements a schedule a budget a Q Monitor and manage product quality Q Measure progress and report performance February 17, 2004 Pat A. Eigbe, PMP® 37
Control Processes II Q Monitor and control risks keep track of identified risks a monitor residual risks a identify new risks a ensure execution of risk plans a assess effectiveness in reducing risk a February 17, 2004 Pat A. Eigbe, PMP® 38
Closing Processes Q Close out contracts Q Resolve any outstanding issues Q Document lessons learned Q Evaluate project Q Archive all project documents February 17, 2004 Pat A. Eigbe, PMP® 39
Conclusion Q Defined Frequently used PM Terminologies Q Discussed Objectives of Adopting Project Management Principles. Q Discussed PM Processes, Tools & Techniques Q Discussed EVMS Overview Q Questions February 17, 2004 Pat A. Eigbe, PMP® 40
References Q Q Q Project Management Institute (PMI), 2000. A Guide to the Project Management Body of Knowledge (the PMBOK® Guide) Stratton R. W. , 1999. Improving SPI and CPI Calculations on LOE Heavy Programs, Proceedings of the 30 th Annual PMI Seminars & Symposium Fleming and Koppeman, 1996. Earned Value Project Management. Ibbs W & Reginato J. , 2002. Quantifying the Value of Project Management Kerzner H, 2003. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. FAST @ http: //fast. faa. gov/wbssec. htm February 17, 2004 Pat A. Eigbe, PMP® 41
Questions/Need Help? http: //pm. act. faa. gov Pat A. Eigbe, PMP® Ext. 5 -7857 patrick. eigbe@faa. gov February 17, 2004 Pat A. Eigbe, PMP® 42
bbb5823de7b503a0886a2500388f39c0.ppt