Mujibar’s House: A Case Study Presented to the DER Shelter Coordination Group Cyclone Sidr, Bangladesh 28 November 2007 FH Bangladesh
Md. Mujibar Rahman, Caretaker, Tk. 5, 800 / month. Own house land in village, but no paddy land. Works in Dhaka: Wife, 1 son, 2 daughters in village. Tin (CGI) house 20’x 18’ with bamboo/wood frame.
The night of the Cyclone District: Madaripur Upazilla: Kalkini Union: Sahebrampur • Built up rice sacks in house; • Violent winds, no tidal surge; • Tree smashed into house: walls gave way, roof collapsed; • Family inside saved by sacks; • Only minor injuries; • Most furniture & household goods severely damaged; • Neighbours houses similarly damaged.
The Following Week • Cleared tree, salvaged households goods, tin and wood. • Took tree to sawmill and cut for frame timber. • Re-shaped bent tin with scrap wood. • Reconstructed house at 15’ by 13’ using old tin, new & old wood, old window and door frames. • Tools: Hammer, screw driver, old hacksaw. • Sundries: Nails, washers, screws, jute. • Labour: Self, father-in-law, brother for two days; Self for further 4 days to finish-out.
The Cost Tree clearer with big saw Tk. 2, 000 $29. 20 Rickshaw van to sawmill Sawmill Bamboo Tk. 500 Tk. 1, 000 Tk. 2, 000 $7. 30 $14. 60 $29. 20 Tk. 250 $3. 65 Tk. 5, 750 $83. 95 Sundries: nails, screws etc. Total cash [Value of tree @ Tk. 700 cu. ft. ] Tk. 10, 000 $146. 00 Total Cost Tk. 15, 750 $229. 95
What Else Would Mujibar Have Liked to Have? • Tools: Proper saw & chisel [+ Spade & pillar hole digging tool]* • Materials: New tin (CGI sheet) for roof: 2 “bundles” = Tk. 9, 000 = $132. • More time to complete verandah and kitchen. • [ Funds to replace damaged household goods. ]* * Ideas added by FH staff
Building Back Better: An example for debate Roof Tin Wall Tin Tk. 9, 000 Tk. 8, 000 $131. 40 $116. 80 Wood Tk. 10, 000 RCC Pillar Tk. 14, 000 $146. 00 $204. 40 Door & Windows Tk. 5, 000 Plinth Tk. 4, 000 $58. 40 Tk. 8, 000 Tk. 58, 000 $116. 80 $846. 80 Labour Total $73. 00 Per: Reza Muhammed Galib, BSc Eng (civil) Better: • RCC Pillars • Brick Plinth But: • Smaller: 14’x 20’ • Still mud floor
Resource Availability May be available in local Union small businesses: • Tin – CGI sheet • Tools • Sawmill • Skilled Labour Need to go to Upazilla town for: • Large supply of Tin • Cement and rod for RCC pillars; • Bricks
Is Mujibar Typical? • • • Has a regular job; Male relatives available to help; Used to work as a building site labourer; No land for cultivation (lives on father-in-law’s land); No water damage from tidal surge. Conclusion – a median case, but many will need livelihood support; BUT: some, particularly those vulnerable before the cyclone, are much worse off. Vulnerable family before Cyclone
Some Strategic Issues • • Affordability: - 1. 2 million homes? Preserving Local Markets for Materials. Stifling or Enhancing Initiative. Cyclone Proof = ? ? Wind Proof, or Tree Fall Proof, or Tidal Surge Proof. Land Availability. Most vulnerable often live outside embankments. Migratory Fisher-families. One size fits all? Vulnerable family before Cyclone