Скачать презентацию Minutes Discussion on the magnetic shielding The Скачать презентацию Minutes Discussion on the magnetic shielding The

5b65fdbc72dd1adc82c2e1672a383460.ppt

  • Количество слайдов: 28

Minutes Discussion on the magnetic shielding: • The magnetic shielding will not be installed Minutes Discussion on the magnetic shielding: • The magnetic shielding will not be installed until the 2016 shutdown. • The magnetic shielding test fixture will be used to develop and verify the design of the shielding. • A measurement probe system needs to be designed that can transit down the test fixture. • After installation, a measurement must be made in the tunnel to confirm that the installed shielding reduces the magnetic field in the beam tube to < 1 m. G. Discussion on 180 dipole • Need information on NMR probe • Should be considered to not install 180 vacuum chamber this shutdown: o NMR probe can be installed in chamber during magnetic measurement o 180 dipole power supply stability could be evaluated during magnetic measurement with NMR probe read backs. Fabrication lead time is a concern. o Can chamber welds could be tested during magnetic measurement? Low Energy RHIC electron Cooling

2 2

Overall Layout 64 m H & V Correctors IP 2 LERe. C-I (1. 6 Overall Layout 64 m H & V Correctors IP 2 LERe. C-I (1. 6 -2 Me. V): Gun to dump SRF gun used as a booster cavity Add Quad and Skew Quad Correctors Move BPM close to 180 magnet combine with PM. Add Quad and Skew Quad Correctors Low Energy RHIC electron Cooling

 • Drawing comes from VAT. • M. Mapes measured one of the new • Drawing comes from VAT. • M. Mapes measured one of the new VAT valves that are in hand found the aperture on the valve flanges on both sides in 2. 480. • Mike will check with VAT on the configuration of the shielded section in the valve. • Mike B. is checking if we should be concerned about the transition from the standard tube I. D. 2. 375” to the valve I. D. 2. 48”. 4

PS Layout Phase 1 Low Energy RHIC electron Cooling PS Layout Phase 1 Low Energy RHIC electron Cooling

PS Layout Cooling Section Low Energy RHIC electron Cooling PS Layout Cooling Section Low Energy RHIC electron Cooling

Brahms Trailer 1002 D Racks ordered on 02: 00 AIP Low Energy RHIC electron Brahms Trailer 1002 D Racks ordered on 02: 00 AIP Low Energy RHIC electron Cooling

180 o Dipole Magnet Neighborhood IV PROFILE MONITOR BPM + YAG + Slit Assemblies 180 o Dipole Magnet Neighborhood IV PROFILE MONITOR BPM + YAG + Slit Assemblies ± 4. 13” HIGH FIELD SOLENOID LOW FIELD SOLENOID H/V Corrector BPM YELLOW RHIC Beam PROFILE MONITOR EMITTANCE SLIT BLUE RHIC Beam BPM Quad/SQ Corrector kh

See slide #2 YELLOW RHIC Beam BLUE RHIC Beam 20 o Dipole Neighborhood IV See slide #2 YELLOW RHIC Beam BLUE RHIC Beam 20 o Dipole Neighborhood IV ERL, Profile Monitor ID=1. 87” BPM PROFILE MONITOR EMITTANCE SLIT HIGH FIELD SOLENOID Cornell, Wire Scanner OD=1. 50” ; ID=1. 38’’ Quad/SQ CORRECTOR BPM w/ ERL Buttons ID=2. 37” YELLOW RHIC Beam BLUE RHIC Beam kh PROFILE MONITOR TRANSPOR T SOLENOID 20° DIPOLE

BPMs in Cooling Section (14 Locations) Large Dia. BPM Housings (4. 8 ID), 28 BPMs in Cooling Section (14 Locations) Large Dia. BPM Housings (4. 8 ID), 28 mm buttons • Order Placed with MPF • Final Design Review 6/23/2015, no issues • MPF approved to start fabrication • Increased number of button first articles for 2 BPM’s one standard, one 180 magnet special • MPF updated delivery schedule • Agreed on vacuum bakeout for components MPF will vacuum bake buttons @900 C/1 hr during brazing MPF will vacuum bake housing @450 C/48 hr BNL will vacuum bake 1 st article housing • First Article delivery buttons 9/12/2015 • First Article delivery housing 10/01/2015 Low Energy RHIC electron Cooling

Cooling Section Standard Profile Monitors RF impedance design approved (Peter T. ) Ferrite ring Cooling Section Standard Profile Monitors RF impedance design approved (Peter T. ) Ferrite ring mounting design complete. CMD 5005 material. Requisition for commercial vacuum linear stage, requisition complete YAG screen/mirror holder design complete. Fabrication drawings for YAG screen/mirror holder and vacuum chamber. Update design for ground fingers. Stage Assembly (Linear Feedthrough) Zero Length adapter flange Profile Monitor YAG Screen Assy. Low Energy RHIC electron Cooling

Cooling Section “hybrid” BPM, Slit RF impedance analysis complete Chamber design complete Need approved Cooling Section “hybrid” BPM, Slit RF impedance analysis complete Chamber design complete Need approved fabrication drawing (CO with MPF? ) Design of RF impedance grounding fingers defined Design of RF impedance ferrite configuration and mounting Low Energy RHIC electron Cooling

Cooling Section PM meeting Notes: • Mirror thickness specified • Both Hybrids PM, Slit, Cooling Section PM meeting Notes: • Mirror thickness specified • Both Hybrids PM, Slit, BPM systems will be 3 position vacuum translating stage drives. The second hybrid will substitute the slit position (which is not needed) for a fault study beam stop. • Dan transverse position accuracy of the vacuum translating stage – will order 2 and measure. • Angle mount windows ordered (7 units). • The windows will be coated with a thin metallic coating by the vendor (KL). • The Yag crystals will be coated with a thin metallic coating to dissipate charge. Dan Steski can do it. • CS has preliminary drawings for standard profile monitor for cost estimate. Need to update and check final drawings. • The grounding requirements for the hybrid head has been revised. Grounding fingers and mounting frame defined. • The standard profile monitor will be modified for grounding fingers in the inserted position. TBD • The emittance slits needs grounding fingers – New grounding finger hardware defined. Low Energy RHIC electron Cooling

Cooling Section Emittance Slits • • • Requisition for commercial vacuum linear stage. Fabrication Cooling Section Emittance Slits • • • Requisition for commercial vacuum linear stage. Fabrication drawings complete and approved. Central Shops requisition approved for vacuum chamber and W slit. The slit needs to be grounded at the vacuum chamber when scanning. Delivery dates: shifter, vacuum chamber, W slit, mounting hardware. Low Energy RHIC electron Cooling

LERe. C collimator thickness considerations P. Thieberger 9/8/2015 Ranges of electrons in Tungsten. The LERe. C collimator thickness considerations P. Thieberger 9/8/2015 Ranges of electrons in Tungsten. The Continuous Slowing Down Approximation (CSDA) ranges obtained from the NIST ESTAR data base are distances along the electron zigzag trajectories. They exceed the penetration depth by the so called “detour factor” obtained as shown on the next slide. Low Energy RHIC electron Cooling

LERe. C collimator thickness considerations P. Thieberger 9/8/2015 Conclusions • For Phase 1, a LERe. C collimator thickness considerations P. Thieberger 9/8/2015 Conclusions • For Phase 1, a collimator tungsten thickness of 0. 4 mm would be adequate while 0. 9 mm would be needed for Phase 2 • It would be advantageous to choose thinnest possible material to alleviate alignment issues and to reduce slit scattering • In any case thicknesses larger than 1 mm don’t seem to be justified for this project. Low Energy RHIC electron Cooling

Vacuum Hardware Beam line bellows & 180 accordion bellows purchase orders. “Standard Chamber Length” Vacuum Hardware Beam line bellows & 180 accordion bellows purchase orders. “Standard Chamber Length” defined – NEG coating underway 180 chamber 316 L vacuum annealed to 900 C after welding. 180 chamber in shops, 20 chamber in shops – 2 only Test chamber welded and measured. Shielded valves on order DC Gun shielded valves and vacuum equipment. Low Energy RHIC electron Cooling

20 o Dipole Magnet Requisition approved SOW – 2 magnets by 10/1/2015. Order Placed 20 o Dipole Magnet Requisition approved SOW – 2 magnets by 10/1/2015. Order Placed 5/6/2015 Everson Tesla Estimated Delivery 1 st two magnets 10/1/2015 Distance Between Pole Faces = 10. 4 cm (4. 1 in. ) Magnet Vertical Gap = 10 cm Vacuum Chamber V Aperture = 9. 5 cm (3. 74 in. ) Low Energy RHIC electron Cooling

180 o Dipole Magnet Revised 19 180 o Dipole Magnet Revised 19

Compensating and Matching Solenoids Buckley magnets complete 8/20/2015? ? + 6 weeks shipping + Compensating and Matching Solenoids Buckley magnets complete 8/20/2015? ? + 6 weeks shipping + customs. Alpha Magnetics update: 1 st production magnet + 9 more in house. Magnetic Measurement ordered and received 1% and 0. 1% 3 D probes 3 D Probes being calibrated Preliminary measurements complete. • Design support stand assembly – provide space for mu metal shields, separate beam pipe stand support. Fabricate Stands • Magnetic shielding analysis (Wuzheng). • Design prototype mu metal shields and supports - measure. Low Energy RHIC electron Cooling

Compensating and Matching Solenoids Feed the BPM cables through a common hole in the Compensating and Matching Solenoids Feed the BPM cables through a common hole in the shielding for each BPM station (4 cables /hole). This will require a 90 degree type-N connector on the LDF 1 -50 Heliax cable (0. 37" OD) that connects to BPM button feedthrough connector. Would you have the design add the cables and connectors to the model and choose an appropriate place for the penetration, respecting the minimum cable bending radius? Low Energy RHIC electron Cooling

Compensating and Matching Solenoids HALL PROBE / SOLENOID GRANITE TABLE (Measurement Schedule) August 3 Compensating and Matching Solenoids HALL PROBE / SOLENOID GRANITE TABLE (Measurement Schedule) August 3 -7: complete permanent magnet measurements August 10 -14: August 17 -21: reconfigure Hall probe (Sullivan), then resurvey (Karl) August 24/25: Jain reviews survey data, first solenoid (Sauerwald) August 26 – Sept. 30: move solenoid granite table out of Annex October first solenoid complete, goal of 2 per week. Low Energy RHIC electron Cooling

Compensating Solenoids Measurement We have done a preliminary scan (on-axis only) to check out Compensating Solenoids Measurement We have done a preliminary scan (on-axis only) to check out the measurement system and the results seem to be good in terms of magnet performance. We tuned the main coil and bucking coil currents to match the central fields expected from Wuzheng's calculations. An adjustment of about +2% had to be made to the design currents to get the design fields. The on-axis field drops below 1 Gauss level at approximately +/- 18 cm from the magnet center. This is a faster fall off than the +/- 21 cm expected. I am not sure if the earth's field of about 0. 2 Gauss is helping with this. The second field integral at the adjusted current settings comes out to be 4. 019 E-05 T^2. m, which meets the 4. 0 E-5 T^2. m requirement. Thanks, Animesh Low Energy RHIC electron Cooling

LERe. C Cooling Section Design Room LF & HF solenoid and 20 o dipole LERe. C Cooling Section Design Room LF & HF solenoid and 20 o dipole magnets fabrication drawings (KH) Beam Diagnostics: BPM chamber and buttons (VDM) Beam Line 5” bellows with shields fabrication drawings (GW) 20 o dipole vacuum chamber for impedence review (KH) 180 o dipole fabrication drawings (KH) Spectrometer magnet (180 o dipole) revisions (KH) 180 o vacuum chamber + large sliding bellows fabrication drawing (KH) Beam Diagnostics ES W slit & chamber fabrication drawings (VDM) 20 o dipole vacuum chamber fabrication drawings (KH) Cable tray and penetration drawings and excel sheet (AF) Beam Diagnostics: standard PM fabrication drawings (GW) Beam Diagnostics: special “hybrid” ES/PM/BPM fabrication drawings (GW) Beam line solenoid/BPM stands & vacuum chamber stand (VDM) Beam line magnetic shielding (VDM) 20 o magnet stand drawing (KH) 180 o magnet w/hybrid BPM stand drawings (KH) Magnetic shielding drawing and solenoid magnetic measurement test station HF dipole, quadrupole, and skew quadrupole corrector drawings Low Energy RHIC electron Cooling

LERe. C Design Room Source Design Work DC Gun Vacuum Chamber Fabrication Drawings (JH) LERe. C Design Room Source Design Work DC Gun Vacuum Chamber Fabrication Drawings (JH) DC Gun SF 6 Pressure chamber specification control drawings (JH) DC Gun cathode cooling design for Karl S. Cornell (JH) DC Gun stands (JH) DC Gun to Booster SRF booster cavity beam line (JH) DC Gun cathode insertion drive (WJ/VDM) DC Gun cathode coating system vacuum chamber (PC) DC Gun cathode transfer load lock and vacuum chamber (WJ) Cathode production coating system design (BM) Low Energy RHIC electron Cooling

LERe. C Design Room Other Work RHIC 1: 00 move real estate drawings (V. LERe. C Design Room Other Work RHIC 1: 00 move real estate drawings (V. DM. ) Phase 2: 5 cell cavity positioning (RM) – Revised Position on hold Phase 1 and 2 cryogenic system layout (RM) 2. 1 GHz warm cavity fabrication drawings (MG) 704 MHz warm cavity fabrication drawings Transport & Merger line layout (RM/VDM) Transport & Merger Line Layout Transport & Merger Line Solenoids Transport & Merger Line BPM’s Transport & Merger Line Profile Monitors Low Energy RHIC electron Cooling

Installation Step – 2015 Shutdown Cooling Section Purchase Orders in Place • HF and Installation Step – 2015 Shutdown Cooling Section Purchase Orders in Place • HF and LF solenoid magnets in fabrication, 1 st article in transit • Shielded vacuum valves, bellows, tuning (sliding) bellows, gauges? • Beam tubes being coated • BPM chambers and buttons ordered FDR approved • 20 o merger magnets • Beamline shielded bellow and 180 o magnet sliding bellows • Profile monitor and emittance slit vacuum linear drives Cooling Section Critical Items (not ordered yet) • 20 o magnet vacuum chamber (MM preparing RFQ) • Special RF vacuum gaskets • Diagnostics chambers & hardware: PM, ES, PM/ES/BPM • Beamline equipment stands • 180 o magnet (spectrometer magnet – moved to 2016) 27

Installation Step – 2015 Shutdown Punchlist Cooling Section Parts in Hand • 5 of Installation Step – 2015 Shutdown Punchlist Cooling Section Parts in Hand • 5 of 15 LF solenoid magnets • 5” beam tubes and flanges • Shielded vacuum valves 28