
07ec6e0cd20f9cf0ca0c1a53aefb86dc.ppt
- Количество слайдов: 14
Me. RHIC Engineering Challenges and Solutions for Me. RHIC Joseph Tuozzolo EIC Stony Brook University January 10, 2010
Key Components Me. RHIC Photoinjector Design – Electron Gun (A. Burrill, 11/2009) “Gatling Gun” multi-cathode Photocathodes & Drive Laser (A. Burrill, 11/2009) Laser development for the required intensity Linac SCRF Accelerator Cavities (A. Burrill, 11/2009) HOM Damper Upgrade, 6 Cavity Types, Cost and Schedule Cryogenic System (A. Burrill, 11/2009) RF systems (A. Burrill, 11/2009) SCRF Development and Design at BNL – Engineering Design Magnet Design Vacuum System RHIC Modifications – Civil and Beam Line Schedule Joseph Tuozzolo EIC Stony Brook University January 10, 2010
Me. RHIC: General layout Pre-accelerator 90 Me. V ERL Electron gun 0. 1 Ge. V Linac 1 Main ERLs; 6 cryomodules x 6 cavities x 18 Mev/cav = 0. 65 Ge. V per linac 0. 1, 1. 4, 2. 7 Ge. V 0. 75, 2. 05, 3. 35 Ge. V Linac 2 4 Ge. V (April 09) IR 2 region features: - asymmetric detector hall (appropriate for asymmetric detector for e-p collisions) - long wide (7. 3 m) tunnel on one side from the IR for energy recovery linac Main components: -100 Me. V injector on the basis of polarized electron gun (50 m. A) and pre-accelerator ERL. -Two main ERLs (one of them in the RHIC tunnel) with maximum 0. 65 Ge. V energy gain per linac. -Recirculation passes are going outside of the existing tunnel: warm magnets, acceptable synchrotron radiation power. Joseph Tuozzolo EIC Stony Brook University January 10, 2010
Me. RHIC SCRF Cavity Development (Ilan’s Talk) Energy Recovery LINAC • 5 Cell SCRF Assembled and Tested at 2 K ERL e Gun • ASME Code compliance design complete • Laboratory Safety Committee Approval • Fabrication underway RHIC 56 Mhz SCRF Cavity • ASME Code compliance design complete • Laboratory Safety Committee Approval • Contract SCRF Vertical Test Facility • ASME Code compliance design complete • Laboratory Safety Committee Approval • Test Dewar & Cryogenic Refrigerator in House • Shielded Enclosure Complete Collaborative Support: JLab, AES, SNS, TRUMPF, Cornell, Amuneal, . . . Joseph Tuozzolo EIC Stony Brook University January 10, 2010 4
SCRF Cavity Development – ASME Code Compliance Me. RHIC Cryogenic Systems need extensive review (DOE Pressure Safety Compliance and LHC Failure) • Detailed Stress Analysis done in house using ANSYS w/peer review • Detailed Cryogenic Analysis to determine proper relief valve sizing w/peer review • Fabrication QA: material testing and certifications, welding procedures and qualification, fabrication in process inspection, leak and pressure testing, certified relief devices, etc. • Final Review and approval by Laboratory Committee Joseph Tuozzolo EIC Stony Brook University January 10, 2010 5
Me. RHIC Magnet Systems Arc Magnets (Conventional, Small Aperture, high accuracy, copper bus magnets) • 361 Quadrupoles, 150 Dipoles, 56 Trim Dipoles, 56 Correctors • Prototype dipole already machined, assembled, and field mapped. • Quadrupole prototype being machined Spreader Combiner Magnets (Dan’s Talk) • 4 Spreader/Combiner conventional dipole magnets, • 10 thin septum magnets, 42 vertical dipole magnets, 68 Correctors SCRF Cavity Magnets • 14 SC Quadrupoles in the SCRF cavity cryostats BNL Design, 1 st Article, Test, Commercial Bid – Built to Print or Build to Specification (SC Quadrupole). Joseph Tuozzolo EIC Stony Brook University January 10, 2010 6
Me. RHIC Vacuum System Layout BEAM VACUUM • 30 VACUUM SECTORS • 10 e-9 Torr pressure in arcs and s. s. • 10 e-10 Torr in baked transition regions • <10 e-10 Torr in SC LINAC • Fully RF shielded components LINAC INSULATING VACUUM • <10 e-3 warm • Turbomolecular pump on each Module Me. RHIC Vacuum I&C • Based on recent system upgrades to AGS/Booster and EBIS Challenges • Stress in small aperture thin wall chambers. • Synchrotron light energy absorber design. (Jo. Anne’s talk). Joseph Tuozzolo EIC Stony Brook University January 10, 2010
Beam Line Modifications Required in the RHIC Tunnel Removal/Relocation of existing RHIC Beam Instrumentation. Removal of both DX magnets/Splice Bus. Install two new Polarized Proton Spin Rotators/modify VJP. Separate Beam Tubes for blue and yellow beam. • Be beam tube. STAR and PHENIX beam tubes. Joseph Tuozzolo EIC Stony Brook University January 10, 2010 8 Me. RHIC
Spin Rotator Installations 1: 00 and 2: 00 Fabricate 2 new Spin Rotators (BNL Magnet Division) Spare Coil Assembly will help schedule Reconfigure Q 4 end for Spin Rotator Coupling New VJP sections required between Q 3 and Spin Rotator New warm to cold fabricated for Spin Rotator/VJP transition Fabricate components to existing drawings 6: 00 and 8: 00 Joseph Tuozzolo EIC Stony Brook University January 10, 2010 9 Me. RHIC
Me. RHIC Remove DX Magnets, Install e Beam Injection Chicane Removal of both DX magnets as a complete units Remove and re-splice Blue SC Bus. DO magnets do not have to be shifted 6 new warm dipoles for beam alignment 2 new wide aperture warm dipoles DX Magnet + Y chamber & ZDC Joseph Tuozzolo EIC Stony Brook University January 10, 2010 10
Me. RHIC Conventional Facilities – Civil Construction Major Additions: Racetrack tunnel with transitions to RHIC tunnel. (possible RHIC schedule issue) • Service buildings with access ports to racetrack • 1 ea – 20 x 150 for cavities, 1 ea – 16 x 40 for ERL, 2 ea -16 x 50 for bends Power • Extension of the 13. 8 Kv overhead line to 2: 00 – 25 MW • 2 ea – 2 ½ MVA unit substations, 1 ea 13. 8/4. 2 Kv transformers, Basic power distribution Cooling water • 3 MW demineralized cooling water system - Basic water distribution Utilities • Extension of the sanitary sewer line, Utility compressed air, Domestic water, Extension of the storm drains, Network / communications ductwork Joseph Tuozzolo EIC Stony Brook University January 10, 2010 11
Summary of C-AD Facility Characteristics Over 1 Million Ft 2 Of Equipment, Office, And Workshop Space 110 Buildings 1000 Acres Of Land 7 Accelerators 400 Direct Staff 22. 5 Allocated Staff 6. 2 Miles Of Vacuum Beam Pipe 24 Miles Of Cable Tray 62 Electrical Substations 1000 s Of Electrical Distribution Circuits 15 Cooling Towers In Service 52 Cooling Systems In Service 1000 s Of Electro-magnets / Power Supplies 1740 Superconducting Magnets in RHIC 26 Compressors For Cryogenics System Power Consumption: 25 MW includes 5 MW for the cryogenic refrigerator. (Me. RHIC: 5. 7 MW cryogenics, 14 MW RF and PS) Joseph Tuozzolo EIC Stony Brook University January 10, 2010 Me. RHIC
Me. RHIC Installation – Schedule Only Four year construction project CD-3 to CD-4 Critical Items must be ordered during CD-1 and CD-2 • SCRF Cavity Fabrication • Tunnel Construction Design • Spin Rotator Magnet Fabrication Long Lead Items will drive schedule RHIC Operations Schedule During Construction New Tunnel tied in 2 years after CD-3 Temporary Shielding at Tunnel Tie-in • Existing 20 Ton Crane! N E W S Joseph Tuozzolo EIC Stony Brook University January 10, 2010 13
C-A Department 50 years of significant upgrades AGS (1960) 80” Bubble Chamber + others (1966) Slow Extracted Beam (1968) 200 Me. V Linac (1970) AGS Polarized Protons/Heavy Ions (1984 - 86) Booster (1990) RHIC Facilities (1980 – 2000) NASA Space Radiation Laboratory (2004) Electron Beam Ion Source, Stochastic Cooling (2010) + Collaborations: SNS, LHC, NSLS, . . . Me. RHIC is another evolution Joseph Tuozzolo EIC Stony Brook University January 10, 2010 Me. RHIC