Mc. Clugage Bridge Rehabilitation
Contract Information: • Joint Venture between Midwest Foundation and Halverson Construction • A+B Bidding • Award Value - 26. 1 Million • 233 Days
Eastbound Structure Peoria East Peoria
Project Schedule: • March 13 th - Close Eastbound Structure • November 1 st - Re-Open Eastbound Structure • Incentive/Penalty - $25, 000/Day • Work Hours - Two 10 Hour Shifts/6 Days Per Week
Traffic Management
Traffic Facts: • ADT - 42, 500 • Morning Rush Hour - 6: 00 AM to 9: 00 AM • Afternoon Rush Hour - 3: 00 PM to 6: 00 PM • Two Way Traffic on WB Structure
Public Relations Integrated into Design
Ensuring Public Relations Success: • Innovative Contracting • Innovative Traffic Management • Aggressive Public Relations Campaign
Innovative Traffic Management: • Moveable Barrier Wall • Automated Real-Time Traffic Control System • Video Surveillance Cameras
Moveable Barrier Wall
N IL 29 US 150/US 24 10: 00 PM to 11: 30 AM
N IL 29 US 150/US 24 11: 30 AM TO 10: 00 PM PM TRAFFIC CONTROL PATTERN Two Lanes Eastbound One Lane Westbound
AM Alignment - 10: 00 PM to 11: 30 AM 12’-4” WB TRAFFIC 2. 0’ 12’-4” EB TRAFFIC
PM Alignment - 11: 30 AM to 10: 00 PM 12’-4” WB TRAFFIC 2. 0’ 12’-4” EB TRAFFIC
Moveable Barrier Machine: • Weighs Approx. 16 Ton • Can Shift Barrier Wall From 4’ to 18’ • Approx. 5 -10 MPH
Benefits of Moveable Barrier System: • Safety • Increase Capacity • Reduce Congestion – Good Public Relations
Towing