LAS VEGAS AQUIFER STORAGE AND RECOVERY PROGRAM Texas Innovative Water 2010 Seminar San Antonio Texas Tom Morris
Physiographic Setting Las Vegas Nevada
Feasibility Evaluation • • • HYDRO-GEO SETTING – Geology Limits – GW Water Quality – Production Yield OTHER CONCERNS – Water Level Declines – Planned Growth – Existing Dist System APPROACH – Basins VS Wells – Old VS New Wells – Recovery Location
Feasibility Evaluation • • • HYDRO-GEO SETTING – Geology Limits – GW Water Quality – Production Yield OTHER CONCERNS – Water Level Declines – Planned Growth – Existing Dist System APPROACH – Basins VS Wells – Old VS New Wells – Recovery Location
Feasibility Evaluation • • • HYDRO-GEO SETTING – Geology Limits – GW Water Quality – Production Yield OTHER CONCERNS – Water Level Declines – Planned Growth – Existing Dist System APPROACH – Basins VS Wells – Old VS New Wells – Recovery Location
Feasibility Evaluation • • • HYDRO-GEO SETTING – Geology Limits – GW Water Quality – Production Yield OTHER CONCERNS – Water Level Declines – Planned Growth – Existing Dist System APPROACH – Basins VS Wells – Old VS New Wells – Recovery Location
Demonstration Operations RECHARGE PREP • Flush Well • Drop Laterals • Flip Flow Meter • Prop Check Open EXISTING WELL CONVERSION • Demo with 2 Wells • Convert 33 wells to ASR • Apparent Well Clogging
Demonstration Operations • • • WELL USE TYPE – Unused Well Conversion – New Dedicated Injection – New ASR Wells ASR WELL DESIGN – Various Drill Methods – Engineered Fluid Control – Injection Development WELLHEAD EQUIPPING – Bi-Directional Flow Meter – Check Valve By-Pass – Automated On-Off Control – Motor Ratchet
Expanded Operations • • • WELL USE TYPE – Unused Well Conversion – New Dedicated Injection – New ASR Wells ASR WELL DESIGN – Various Drill Methods – Engineered Fluid Control – Injection Development WELLHEAD EQUIPPING – Bi-Directional Flow Meter – Check Valve By-Pass – Automated On-Off Control – Motor Ratchet
Expanded Operations • • • WELL USE TYPE – Unused Well Conversion – New Dedicated Injection – New ASR Wells ASR WELL DESIGN – Various Drill Methods – Engineered Fluid Control – Injection Development WELLHEAD EQUIPPING – Motor Ratchet – Bi-Directional Flow Meter – Check Valve By-Pass – Automated On-Off Control
Expanded Operations • • • WELL USE TYPE – Unused Well Conversion – New Dedicated Injection – New ASR Wells ASR WELL DESIGN – Various Drill Methods – Engineered Fluid Control – Injection Development WELLHEAD EQUIPPING – Motor Ratchet – Bi-Directional Flow Meter – Check Valve By-Pass – Automated On-Off Control Isolation Gate Valves Pump Check Valve Recharge Start/Stop Auto Valve
Managed Operations • • • HYDRO-GEO EFFICIENCY – Geology Zones – Water Level Impact – Recharge Migration WELL OPTIMIZATION – Maximize Recharge Rates – Piping Efficiency – Scheduled O & M SYSTEM RELIEF – Peak Demand Supply – Commercial P&T
Managed Operations • • • HYDRO-GEO EFFICIENCY – Geology Zones – Water Level Impact – Recharge Migration WELL OPTIMIZATION – Maximize Recharge Rates – Piping Efficiency – Scheduled O & M SYSTEM RELIEF – Peak Demand Supply – Commercial P&T
Managed Operations • • • HYDRO-GEO EFFICIENCY – Geology Zones – Water Level Impact – Recharge Migration WELL OPTIMIZATION – Maximize Recharge Rates – Piping Efficiency – Scheduled O & M SYSTEM RELIEF – Peak Demand Supply – Commercial P&T
Lessens Learned PRE-DEVELOPMENT CONDITIONS Alluvial Course Gravels 80 Years of Basin Overdraft Lowered Water Table 100 to 300 Feet Pediment Sands and Gravels Playa Lake Bed Sands and Silts
Lessens Learned HYDRO-SYSTEM CHANGES Development and Irrigation Created Un-Natural Shallow Aquifer Perched Water System Development Surface to 35 -Feet
Lessens Learned RECHARGE AQUIFER RECOVERY 16 Years of Recharge 320, 000 AF Banked Perched Water System Development Surface to 35 -Feet
Lessens Learned OTHER RECHARGE PROGRAM RELATED ISSUES • Disinfection By-Products • Water Quality Plume • Pump Wear and Sanding • Dissolved Air
Visions of Hope Questions?