Скачать презентацию Injector Status Timur Shaftan Injector Group Leader 9 Скачать презентацию Injector Status Timur Shaftan Injector Group Leader 9

d50b0a6b114067af9ad7da3371b7ea83.ppt

  • Количество слайдов: 20

Injector Status Timur Shaftan, Injector Group Leader 9 th ASAC meeting for NSLS-II Project Injector Status Timur Shaftan, Injector Group Leader 9 th ASAC meeting for NSLS-II Project February 1 -2, 2012 1 BROOKHAVEN SCIENCE

Outline • • Introduction Project baseline dates Preparation for linac commissioning Status of the Outline • • Introduction Project baseline dates Preparation for linac commissioning Status of the booster system Status of the transport lines Status of SR injection straight section Conclusions 2 BROOKHAVEN SCIENCE

Injector Layout BST Phase One SR Injection Straight BST Phase Two Linac Booste r Injector Layout BST Phase One SR Injection Straight BST Phase Two Linac Booste r LTB Phase Two 3 LTB Phase One BROOKHAVEN SCIENCE

Introduction • Linac: finishing installation; commissioning is coming in March-April 2012 • Booster: in Introduction • Linac: finishing installation; commissioning is coming in March-April 2012 • Booster: in the middle of production; first container is delivered, second is on the way (total 13) • Lt. B transport line: 1 st part is installed; unit testing is ongoing; integrated testing is in middle of Feb 2012 • Lt. B TL part 2 and BST TL part 1: design is finished; procurements are ongoing • BST transport line part 2: design is concluded • Injection straight section: septum contract is awarded (Danfysik) in late Aug 2012; kickers we are building in-house 4 BROOKHAVEN SCIENCE

Injector Complex Status Linac BST-TL (Phase One) Booster Injection straight section LBT-TL (Phase One) Injector Complex Status Linac BST-TL (Phase One) Booster Injection straight section LBT-TL (Phase One) B. Wahl 5 BROOKHAVEN SCIENCE

Injector Timeline B. Wahl 6 BROOKHAVEN SCIENCE Injector Timeline B. Wahl 6 BROOKHAVEN SCIENCE

Linac Front End Performance – Single Bunch Mode • • • Tests of gun Linac Front End Performance – Single Bunch Mode • • • Tests of gun and SHPB performance Test stand at SDL is developed Linac Front-End is delivered prior to linac delivery for experiments 3 pulsers were tested Beam envelopes along the set-up are measured Measurement data was taken and now being analyzed and compared with model Measured: Bunch Charge: 230 p. C Bunch Length: 437 ps Emittance: 20 mm-mrad R. Fliller and X. Yang 7 BROOKHAVEN SCIENCE

Booster Assembly, Delivery and Installation (Budker Institute of Nuclear Physics) Shipments: Production Integration Magnetic Booster Assembly, Delivery and Installation (Budker Institute of Nuclear Physics) Shipments: Production Integration Magnetic Measurements Prepare for Shipment Transportation Packaging (Girders) Receipt at BNL Packaging (Pedestals) • A total 13 Containers will be shipped to BNL • All Pedestals received 1/4/12 • First Container w/ Girders due 2/20/12 • Containers arrive at BNL every two weeks • Last Container due to arrive June 2012 Installation: • Installation of Pedestals 1/24 – 2/29 • All Girders will be tested in the Experimental Hall Assembly • First Girder will be installed at the end of March • 5 - 7 Girders are installed per week • Last Girder is Installed at the end of August 2012 • Girder Integration complete – 8 BROOKHAVEN SCIENCE

Booster dipoles d. K 1/K 1 d. K 2/K 2 tolerance 170 Me. V Booster dipoles d. K 1/K 1 d. K 2/K 2 tolerance 170 Me. V 3 Ge. V • Dipole production is in progress • Magnetic measurements (above) show that field components are within tolerances • Magnetic measurement system includes array of 16 Hall probes and laser-tracker for controlling position of the sensors inside dipole • 8 BF/ 8 BD are ready: magnet storage area at BINP (right photo) 9 BROOKHAVEN SCIENCE

Booster Power Supplies Corrector/Sextupole PS (BINP) BD PS (Danfysik) • Booster PS: • All Booster Power Supplies Corrector/Sextupole PS (BINP) BD PS (Danfysik) • Booster PS: • All PS are under testing now; • 2 BD and 1 BF circuits: produced by Danfysik. delivery to BNL in April • 3 Quadrupole circuits • Integration with controls was • 16 Sextupole circuits produced by BINP tested at BINP • 36 corrector circuits • Final tests with NSLS-II controls and on full load after delivery 10 BROOKHAVEN SCIENCE

Booster vacuum and diagnostics • Booster arc chambers are complete • Chambers were installed Booster vacuum and diagnostics • Booster arc chambers are complete • Chambers were installed in magnets and vacuum-tested • 12 ceramic chambers have been delivered from Friatec; will be installed into a kicker to measure waveform quality • First septum chamber is being assembled at BINP • BPM buttons delivered to BINP, installed, BPM response measured • Striplines are ready Booster arc chambers Kicker ceramic chamber (Friatec) Complete BPM assembly 11 BROOKHAVEN SCIENCE

Booster pulsed magnets Include: Septum PS • 6 booster kickers • 2 septa • Booster pulsed magnets Include: Septum PS • 6 booster kickers • 2 septa • Slow bump • Injection kicker (below) is developed and tested; performance is within spec • Extraction kicker will be available for testing in February • Septum magnet will be assembled in February, PS is ready • Bump magnets and their PS are ready and in testing • After delivery all booster pulsed magnets will be assembled and tested in NSLS-II Pulsed Magnet Lab. Injection kicker waveform Injection kicker test-stand at BINP 12 BROOKHAVEN SCIENCE

Transport Line Magnet Status (Stangenes Industries) LBT Status • LBT 48 mm Dipole (2 Transport Line Magnet Status (Stangenes Industries) LBT Status • LBT 48 mm Dipole (2 of 4 received) BST 90 mm Dipole Small Correctors – Received in Full LBT 100/45 mm Correctors LBT 52 mm Quad (received in full) • Large Correctors – Received in Full • (7 of 18) “Normal Quads” Received • “Large Quads” - Received in Full • (2 of 5) Dipoles Received (work in progress – May 2012) (7 of 17 received) ***** Balance of Magnets expected May 2012***** BST Status • BST 52 mm Quad (18) “Long” Quads Expected May 2012 (work in progress – May 2012) LBT 134 mm Quad (received in full) • (4) Dipoles Expected May 2012 **** LBT & BST “Spares” Expected June 2012***** B. Wahl 13 BROOKHAVEN SCIENCE

LBT - Phase One Installation/Testing LTB-TL (Upstream) Current Status: LTB-TL (Downstream) • Magnets, Diagnostics LBT - Phase One Installation/Testing LTB-TL (Upstream) Current Status: LTB-TL (Downstream) • Magnets, Diagnostics and Vacuum installed • DI Water and CA connections complete by 2/14 • Electrical Utilities complete by 2/7 Shielding • Vacuum complete by 2/16 Magnets • Interlock complete by 2/15 • Shielding complete by 2/17 • Final survey scheduled for the week of 2/6/12 • Integrated Testing scheduled between 2/13 – 2/24 Diagnostics Survey & Alignment • IRR Committee conducts review between 2/13 – 2/17 • ARR takes place between 2/27 – 2/19 B. Wahl 14 BROOKHAVEN SCIENCE

Injector Control Room * Control room: top view As of Jan 20 th 15 Injector Control Room * Control room: top view As of Jan 20 th 15 BROOKHAVEN SCIENCE

Status of BSR transport line • BST transport line design is complete • BSR Status of BSR transport line • BST transport line design is complete • BSR TL Final design review took place in Sept 2011 • Delivery of all TL magnets are expected from Stangenes until June 2012 • Detailed design of vacuum chambers is on the way • Most diagnostics components are the same as in Lt. B TL • Software applications for booster commissioning using BST TL diagnostics line have been tested Booster extraction straight BSR transport line 16 BROOKHAVEN SCIENCE

SR kicker development • Aug 2011 -- decision to build 5 kickers in house SR kicker development • Aug 2011 -- decision to build 5 kickers in house • Ceramic chambers are on order • Testing IGBTs and Behlke switches • Pulser prototype is tested at half of the nominal voltage (stability of I/I<3 E-5 is achieved) • Kicker field measurement system is developed Kicker pulser prototype Ceramic kicker chamber Kicker field measurement system E. Blum, P. Zuhoski, R. Heese, S. Kowalski, B. Singh 17 BROOKHAVEN SCIENCE

SR injection straight section • DC preseptum is identical to the booster extraction septum SR injection straight section • DC preseptum is identical to the booster extraction septum • Compact design with low fringe field • Septum PS by NSLS-II Electrical group • Tender for the SR pulsed magnets was concluded in July 2011 • Danfysik received the septum contract • “Usual” out-of-vacuum design such as at Diamond or ASP • Danfysik will deliver the magnet, chamber, PS (PPT), controls • Septum PDR is on February 9 th DC preseptum SR pulsed septum • SR injection straight section: we E. Blum, are designing the interface P. Zuhoski, R. Heese, S. Kowalski, B. Singh chambers between pulsed BROOKHAVEN SCIENCE 18

Conclusions • • We are at the start of injector commissioning Linac ARR is Conclusions • • We are at the start of injector commissioning Linac ARR is scheduled for Feb 29; commissioning is in mid March Booster delivery and installation throughout summer and early fall Close interaction with all injector vendors: RI, BINP, FRIATEC, Danfysik, PPT 19 BROOKHAVEN SCIENCE

NSLS-II team working on injector G. Wang, B. Wahl, R. Fliller, E. Blum, J. NSLS-II team working on injector G. Wang, B. Wahl, R. Fliller, E. Blum, J. Rose, R. Heese, S. Kowalski, B. Dalesio, B. Parker, F. Willeke, S. Ozaki, E. Johnson, E. Weihreter, Y. Li, I. Pinayev, M. Ferreira, S. Klare, M. Johanson, B. Singh, P. Zuhoski, G. Fries, A. Blednykh, S. Sharma, G. Shen, K. Shroff, T. Mennona, B. Kosciuk, D. Hseuh, G. Ganetis, T. Shaftan, O. Singh, J. Skaritka, C. Spataro, E. Golnar, P. K. Job, B. Casey, G. Woods, X. Yang, L. Yang, A. Ackerman 20 BROOKHAVEN SCIENCE