Substation Business Applications using CIM / PI AF by Stephen Diebold Manager – Real Time Systems Kansas City Power & Light
Agenda • Overview of KCP&L • CIM / PI AF Project ü A Convergence of Opportunities ü Main Goal ü Situation Without Project ü Closing the Loop ü Asset-Related Applications ü Applications • Interoperability Test • Project Status • Questions
• Over 810, 000 customers • Peak in excess of 5, 660 MW • Service territory across 47 counties in MO and KS covering 17, 934 sq. miles • Over 3, 170 employees • 30 office/service center locations • 9 generation plant sites and 10 peaking facilities • 3, 309 miles transmission lines • 24, 466 miles of overhead distribution lines • 3, 400 miles of underground distribution lines • 322 substations
CIM/PI AF Project A Convergence of Opportunities • EMS comes with PI Historian – Stores history of EMS real-time point data – PI features for model-based access to tags – Utilizes standards-based CIM model for EMS database configuration
CIM/PI AF Project Main Goal Transmission Engineering Interest in moving from Event-based maintenance to Condition-Based Maintenance
CIM/PI AF Project Situation Without Project § EMS gathering 50, 000+ points of real-time data § CIM database where equipment and associated real-time data points defined for EMS AF § Point data history stored in PI tags, PI Server but accessible only by point name . . § PI product (AF) able to model equipment’s relationships to tags, but product not currently used . . CIM DE Environment EMS field devices
CIM/PI AF Project Closing the Loop üExport CIM model data to PI AF product üCreate PI equipment / asset model for retrieving historic tag data • Create infrastructure for generalized retrieval of historic real-time information AF PI Server GDA (Utility Integration Bus) . . – on equipment basis (by reference to equipment location in system) – on asset basis no matter where asset has been moved in system • Generalized retrieval is essential to the creation of applications . . CIM DE Environment Network Manager EMS field devices
CIM/PI AF Project Asset-Related Applications üCondition-Based Maintenance Applications for transformers and breakers Condition-Based Maintenance Applications AF Asset Management System PI Server GDA (Utility Integration Bus) . . • • Desktop access Paging/Email notification Web access First step toward “dashboard” access to real-time Operations data . . CIM DE Environment Network Manager EMS field devices
Interoperability Test • Demonstrate interoperability between ABB, SISCO and OSISoft’s products based on the CIM and/or GDA. • Verify compliance with the CIM for those CIM classes/attributes involved in the information exchanges. • Demonstrate the exchange of power system models using the CIM and an RDF schema and XML representation of the model data. • Demonstrate exchange between ABB and SISCO products using the services defined in the GDA Client and Server interface standard.
Interoperability Test Vendor ABB OSISoft, LLC SISCO, Inc. Product Name • Network Manager, CIM DE Toolkit Tests • Full Import using CIM XML and GDA services • Incremental Import using CIM XML and GDA services • PI AF • Storage of the ABB model data • PI System Explorer • Review and browsing of the ABB model data • Part number: UIBPIWRAP-412 -095 Version 2. 0. 0 Beta • PI Adapter • Full Import using CIM XML and GDA services • Incremental Import using CIM XML and GDA services • Provide UIB message bus for transport and communication
Project Status • FAT completed June 4, 2010 • Interoperability tests completed June 9, 2010 • SAT is being scheduled
Questions Condition-Based Maintenance Applications AF Asset Management System PI Server GDA (Utility Integration Bus) . . CIM DE Environment Network Manager EMS field devices
Contact information: Stephen. Diebold@KCPL. com December 15, 2007