Data Communications Implementation Team (DCIT) Trials Activities/DTAP Update Schedule Timelines Matt Maki Federal Aviation Administration
DCL Trials Update • DTAP Development Work Ongoing: Requirements firming towards June 7 CDR FAA/Thales bi-weekly TIMs ongoing Facility rep CHI Working Session #1 Complete CHI modifications complete for CHI WS #2 (June 5 -6) DTAP delivery scheduled for Aug 17 delivery to FAATC • MEM Coordination Activities: 5/8 visit to MEM to review DTAP display and equipment sizing/placement options with ATC and Tech Ops reps Preferred equipment locations sent to ESA Tech Ops CM for permanent assignment by MEM Tech Ops Management Reviewed Draft Training and Trials Planning materials/logistics Federal Aviation Administration
MEM DTAP Monitor Clearance Delivery Position • DTAP 15” display to reside beside TDLS 15” display (base mount) • NATCA/ATC collaboration on display location/placement DTAP TDLS Maintains clear visibility to airfield and gate areas from CD and SUP positions • BONUS ? – CAN YOU GUESS WHO THIS IS? • Strip Printer Desktop Keyboard/Mouse Federal Aviation Administration 3
MEM - Space For DTAP Automation Rack and FTI Communications Connections – Preferred Option #1 Contractors Allowed 24 Hour Access with Badge/Proxy Fiber, CAT 5, Copper Cabling Options to Tower Empty 19” Equipment rack cabled to power in T 1212 Would fit DTAP automation CPU if available T 1212 Electronic Equipment Room FTI connections to basement Demarc Otherwise space for a new DTAP 19” rack space is required in T 1212 Federal Aviation Administration 4
MEM - Space For DTAP Automation Rack and FTI Communications – Alternate Option #2 Contractors Allowed 24 Hour Access with Badge/Proxy Fiber Only Option to Tower FTI Demarc Location DTAP Communications to ZME HADDS and ARINC/SITA CSPs Basement Communications Room Existing and New Rack Space Options ID’ed Federal Aviation Administration 5
DCL Trials Update • FTI/ISS Architecture: Initial Trials SCAP Documentation package complete Meeting with ISSM office to review docs pending FTI architecture design complete (part of ISSM Doc package) NAIMES issued DTAP IP assignment complete IPs sent to HADDS configuration team for inclusion in July build/field ZME deployment • FAA-FDX MOU Draft Review complete: FDX review of language complete Agreement signatures pending Same MOU template expected with UAL and DAL Federal Aviation Administration
DCL Trials Update • Trials SRMD Approved: Final signatures complete MEM, EWR, ATL ATC panel representation Attached to Test NCP Case Files • Test NCP Update: (5) Technical, Space, Power, HADDS, Rev # Test plan documents approved and baselined with CMRT HCS Rev # and HADDS interface NCPs approved via CCB New FDIO Echo Port Test NCP in development (CMRT baseline on June 6) Federal Aviation Administration
DCL Trials Update • Trials CSP Service: Boeing/ARINC/FAA contract pending POP begins 6/1 – thru 12/1 Initial p. DTAP AFN testing possible by mid-June via ARINC Boeing/SITA Contract status pending (mid-July? ) KMEM, KACY log in addresses assigned FAATC Data Comm lab FNTB-FEP/CSP connectivity pending Federal Aviation Administration