Скачать презентацию CRT Test area KEK Fuji Tomokatsu Скачать презентацию CRT Test area KEK Fuji Tomokatsu

b61e43afa5b013f63b663698617548f8.ppt

  • Количество слайдов: 21

CRT / Test area @ KEK Fuji Tomokatsu Hayakawa Nagoya University 12 th B CRT / Test area @ KEK Fuji Tomokatsu Hayakawa Nagoya University 12 th B 2 GM 2012/7/23 1

TOP assembly room & TOP preparation/test area 12 th B 2 GM 2012/7/23 2 TOP assembly room & TOP preparation/test area 12 th B 2 GM 2012/7/23 2

(B 4) • ATLAS (TGC) Panel House @ KEK Fuji (B 4) reused as (B 4) • ATLAS (TGC) Panel House @ KEK Fuji (B 4) reused as “TOP assembly room” (Construction completed @ June 23 rd) • Tent constructed @ side space for preparation & test area (Construction completed @ July 5 th) • Provision of infrastructure: Done (thanks to Adachi-sensei & Hayashi-san) • Now ready to start our studies @ Fuji PID mornning meeting Slide from Horii-sensei (2012/05/24, PID meeting) 2018/3/15 3

TOP assembly room Buffer room Dark room 12 th B 2 GM Buffer room TOP assembly room Buffer room Dark room 12 th B 2 GM Buffer room • Clean Buffer Room (Cleanliness Level: ISO 7) • Quartz temporary storage Ø ATLAS Panel House which has 1 big FFU   (Clean air dumpers not worked yet) • Clean Dark Room (Cleanliness Level: ISO 6) • Quartz acceptance test & glue • Installation into QBB Ø “Clean Dark booth” that has 12 FFUs   in the Panel House 2012/7/23 4

TOP assembly room (Cleanliness Level) Limit Lab. visit maintenance Buffer room Limit Dark room TOP assembly room (Cleanliness Level) Limit Lab. visit maintenance Buffer room Limit Dark room Clean Booth Setup Commissioning Quartz Measurement • Buffer Room FFU & Clean Dark Booth work well. • Performance:  Class 100(Dark) / Class 1000 (Buffer) (1 worker) achieved easily. • Quartz: Bring some dust Procedure to be improved 12 th B 2 GM 2012/7/23 (Worker training is also important. ) 5

Fuji Side Space (Preparation / Test area) 12 th B 2 GM • Preparation Fuji Side Space (Preparation / Test area) 12 th B 2 GM • Preparation / Test area • Cosmic-Ray Test (CRT), HV test, QBB, Front. End, … • Any others? • Space (is limited. Please share the tables/racks etc ) • CRT stand: 400 cmx 490 cmx 500 cm(H) • CRT DAQ, HV test, …: 300 cmx 250 cm(H) • Electronics & PMT, …: 250 cmx 200 cmx 250 cm(H) • Mechanics: 240 cmx 490 cmx 500 cm(H) 2012/7/23 6

CRT preparation 12 th B 2 GM 2012/7/23 7 CRT preparation 12 th B 2 GM 2012/7/23 7

Cosmic-Ray Test (CRT) • • Originally proposed by Gray-sensei • • Start/Timing counter o Cosmic-Ray Test (CRT) • • Originally proposed by Gray-sensei • • Start/Timing counter o Modified Belle TOF counter • 40 mm. X 60 mm. X 200 mm • Scinti. Bar viewed by 2 FM-PMTs • 4 layers (t resolution~40 -50 ps) Trigger Counter o Nominal Bell e TOF counter Range Stack Ø Beta selection & shower blocker o Fe blocks: 1 -1. 5 m (t) o And/or Lead blocks Tracker Ø Sci. Fi tracker Transporter… Stand…

CRT preparation • Counter o o o 5 Shortened TOF counters (20 cm) tested CRT preparation • Counter o o o 5 Shortened TOF counters (20 cm) tested in May Read out: CAMAC ADC + TDC Intrinsic time resolution: 80 -100 ps (w/o position correction) • ΔTOF (4 layers) ~ 80 -100/ sqrt(4) = 40 -50 ps (to be refined) • Tracker o o o Nagoya Sci. Fi Tracker under preparation @ Nagoya U. • Sci. Fi planes already prepared by Matsuoka-san • Front-end Board mass(? ) production ASAP Read out: CAMAC TDC (3377) Expected position resolution: 0. 3 -0. 6 mm • Block o o 12 th B 2 GM Iron: 1 m X 0. 5 m X 0. 25 m iron block x 6 Concrete: 1 m. X 2 m. X 0. 5 mx 8 • Stand o …. 2012/7/23 9

CRT preparation Schedule Deadline (CRT) Jul Aug Counter Deadline (LEPS) Sept Oct Nov Dec CRT preparation Schedule Deadline (CRT) Jul Aug Counter Deadline (LEPS) Sept Oct Nov Dec Test (t resolution etc. ) Production Tracker Assembly (~80 ch) Production HV CAEN HV module test Repair @ CAEN Shipping for LEPS beam test Stand Design & construction by ? ? Final CRT stand Construction(? ) Backup option Blocks / parts etc. LEPS beam test preparation LEPS beam test Nagoya TOP meeting 2012/7/18 10

CRT stand a proposal (backup option) • A well-designed CRT stand o Quite important CRT stand a proposal (backup option) • A well-designed CRT stand o Quite important for CRT. I totally agree. No objections. . . • Reviews and beam tests in the near future o Assembly space and “test bench” in the tent to be prepared @ the beginning of Sept…. • Tight construction schedule o Very tight to fix the design & to construct it @ KEK Fuji B 4 by the middle of August o It seems that we don’t have enough materials / parts for CRT stand yet… • A proposal / backup option o Very temporary CRT setup (only for data taking this summer) only if well-designed CRT stand is not ready. o Arrangement : ~1 week, Construction: ~1 week, Assembly: ~2 week ~1 month o The setup to be disassembled ASAP when the well-designed stand is ready 12 th B 2 GM 2012/7/23 11

Simplest CRT setup (2012 summer) • Only materials / parts prepared @ KEK now Simplest CRT setup (2012 summer) • Only materials / parts prepared @ KEK now • Save-saving design (enough space for scaffolding & rolling tower) • Fast & easy construction (~ 1 week) + operational test (~ 1 week) Access ~1 m Al frame Belle ACC / Gas Cherenkov(? ) Access TOP (Al support frame) Rolling Tower (or scaffolding) Nagoya Tracker 1. 8 m Trigger/Timing Counters (20 cm TOF x 4 layers) Iron 1 m(t) C-shape blocks (or Al support frame Belle TOFx 1 1. 3 m 12 th B 2 GM Floor level Access Iron blocks 1 m X 0. 5 m X 1 m(t) (or Lead + Iron blocks) 3. 3 m Access 2012/7/23 12

Summary • TOP assembly room & preparation / test area are ready. o Enough Summary • TOP assembly room & preparation / test area are ready. o Enough cleanliness level in the Panel house easily achieved if users perform proper maintenance work regularly. o Tent for TOP preparation / test constructed. o Let’s (re)start QBB / electronics / Cosmic-ray test @ KEK Fuji. • CRT preparation on going o Counters / Trackers for the CRT under preparation @ KEK and Nagoya o Some iron / concrete blocks also reserved in May • Pb blocks not found yet (What size is the block? ) o CRT setup: A backup option proposed • One of the simplest CRT setups (only for data taking this summer) • Fast & easy construction is a key point due to the tight schedule. 12 th B 2 GM 2012/7/23 13

backup 12 th B 2 GM 2012/7/23 14 backup 12 th B 2 GM 2012/7/23 14

Shielding Blocks prepared for “Range stack” • 1 m X 0. 5 m X Shielding Blocks prepared for “Range stack” • 1 m X 0. 5 m X 0. 25 m iron block x 6 • 1 m. X 0. 5 m iron block x ? ? ? (Adachi-san’s blocks) • 1 m. X 2 m. X 0. 5 m concrete block x 8 01 2 from e Slid ID P /5/10 2 g eetin m • We don’t have many blocks. Which combination do you prefer? (option 1) – thickest -- 1 m X 0. 5 m X 1. 5 m (t) (option 2) -- ? ? ? ? -- 2 m X 0. 5 m X 1 m(t) + 1 m X 0. 5 m (t) (option 3) – widest -- 3 m X 0. 5 m (t) 12 th B 2 GM 2012/7/23 15

Other Blocks • C-shape concrete blocks x 7 o 1. 2 m. L type Other Blocks • C-shape concrete blocks x 7 o 1. 2 m. L type x 7 o 1. 0 m. L type x 7 Stage (work bench) ? g 1. 2 m or 1 m m e fro id Sl 1. 5 m 0. 56 m (0. 83 m Thick) 12 th B 2 GM 2 /10 12/5 0 tin mee ID P 1. 8 m 2012/7/23 16

β selection • Range Stack (+ Shower blocker) • 1 m-1. 5 m (t) β selection • Range Stack (+ Shower blocker) • 1 m-1. 5 m (t) Iron blocks • Thickness is one of main constraints   on CRT stand.    Other heavy materials (Pb? )? Easy to get them @ KEK? Accept(? ? ) 12 th B 2 GM • Other possibilities • CO 2 Gas Cherenkov Counter + thin iron block (shower blocker) Now under study @ KEK… 2012/7/23 17

Fuji B 4 (5/10 10 H 00) • Scaffolding (a candidate) 12 th B 2 Fuji B 4 (5/10 10 H 00) • Scaffolding (a candidate) 12 th B 2 GM 2012/7/23 18

Floor layout (in the tent) CRT area 4 m Scaffolding 4. 75 m Scaffolding Floor layout (in the tent) CRT area 4 m Scaffolding 4. 75 m Scaffolding Setup (C-shape blocks) Rolling Tower (option) 12 th B 2 GM • Installation / Construction crane operation (by Futaba or Hitachi) KEK safety regulations to be checked. • Scaffolding / Rolling Tower Important to access to the setup. 2012/7/23 19

Fuji Side Space (Preparation / Test area) 12 th B 2 GM 2012/7/23 20 Fuji Side Space (Preparation / Test area) 12 th B 2 GM 2012/7/23 20

12 th B 2 GM 2012/7/23 21 12 th B 2 GM 2012/7/23 21