c3bd5b0d091f37693a7b6c9223905ca1.ppt
- Количество слайдов: 20
CEA activities in the frame of SLHC-PP/WP 7 Development of critical components Task 7. 2 : Field stabilization in pulsed sc low beta cavities S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
1) From CARE/ HIPPI • 704 MHz RF power test stand • Cry. Ho. Lab • Available prototypes 2) Test and characterisation • Cavities • Couplers • Tuners 3) Study of RF system in pulse mode • LFD compensation • LLRF S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
HV Pulsed Generator 110 KV ; 25 A ; 50 Hz HVPS 330 KVA DC Klystron 704 MHz – 1 MW 50 Hz – 2 ms - In 2007 & 2008, the klystron was operated at 1. 2 MW at full d. c. - As a consequence of the breakdown of some HV diodes, the HV is still limited to 90 k. V due to the degradation of oil in the HVPS tank ( Prf limited to 800 k. W at full d. c. ) S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
- LN 2 shield, cryogenic circuits and controls are ok - 700 MHz RF tests at few hundreds Watt have been performed - We need to connect the last pieces of wave guide for the high RF power tests S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
From CARE/HIPPI 704 MHz 5 cells beta=0. 5 cavity after welding of LHe tank S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
From CARE/HIPPI 704 MHz high power couplers 100 mm diameter - 50 W doorknob (air) vacuum gauge He cooled OC water cooled RF window cryostat flange electropolished & water cooled IC S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
In vertical cryostat: Eacc=13 MV/m at Qo=1 e 10 • Rs = 6 n. W • Field emission onset 12 MV/m • Quench at 15 MV/m In Cry. Ho. Lab: - Eacc>12 MV/m at Qo=1 e 10 - Qualification of the mag. shielding Qo at low field unchanged S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
Lorentz force detuning coefficient of beta=0. 47 sc cavity: Very good result KL = -3. 8 Hz/(MV/m)2 External stiffness: 33 – 200 k. N/mm S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
SLHC-PP Objective: §Study and development of a correction algorithm for LFD able to limit the variation of the phase during the beam pulse in order to achieve more easily the required field stability §Implementation and measurement in pulsed mode on a real sc cavity beta Eacc [MV/m] KL static detuning [Hz/(MV/m)2] % BW [Hz] 0. 47 (HIPPI) 13 -3. 8 (meas. ) 642 110 0. 65 (SPL - IE) 19 -2 (simul. ) 720 113 1 (SPL - HE) 25 -0. 6 (simul. ) 376 64 1 (FLASH) 23. 6 -0. 7, -0. 9 (meas. ) 390, 501 90, 116 § If the KL for SPL-HE cavities can be lowered down to -0. 6, LFD compensation should not be an issue § To be checked for IE cavities (very close to FLASH cavities) § b=0. 47 sc cavity characteristics are similar to those of IE cavities: good candidate for testing the LFD compensation system S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
High power tests in progress: þ assembly of couplers on the power test bench þ UHV baking (4 days – from 100 to 180° C) þ mounting of the doorknobs þ connection to cooling system and RF waveguide þ test of interlocks þ RF power processing in TW RF power processing in SW S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
In TW mode (full d. c. = 2 ms - 50 Hz): Pdirmax @ full d. c. = 600 k. W Pdirmax @ half d. c. = 800 k. W S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
Operation of the cavity b=0. 47 in pulsed mode Filling time=300 ms, flat top=1 ms, frep=50 Hz Qex = 1. 106 , Eacc= 13 MV/m 4 x. Pflat=230 k. W Pklystron tcav ln 2 flat top generation 4 x. Pflat 4 × tcav ln 2 Vcavity S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009 time
PK φCav+ φk Δφ PK/4 tbeam t 0 φk t 0 t off klystron phase loop φCav+ φk tbeam t on ΔφP=30° S. Chel t 0 dt<10µs tbeam t SLHC-PP meeting, CERN, 25 -26 February 2009 t 0
700 MHz Klystron RF regulation 20 d. B Coupler 704 MHz Phase Shifter JSPHS 1000 sc cavity Preamp PIN diode Att PID Amplitude Regulation K Amplitude detector 60 d. B Coupler 20 d. B Coupler Variable Attenuator (step 0. 1 to 10 d. B) Vref Labview VControl PID Phase Regulation S. Chel Vε AD 8302 Phase Comparator SLHC-PP meeting, CERN, 25 -26 February 2009 Manual Phase adjust
What is already available: þ b=0. 47 sc cavity quenching above 13 MV/m þ LFD compensation system (with manual tuning of PZT drive pulse i. e. pre-delay, amplitude and rise time) þ RF power generator (> 250 k. W) þ Horizontal cryostat þ Helium liquefier, compressor, pumping system S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
What is almost available (will be available in the next 6 months): þ coupler processed above 250 k. W in SW þ tuning system with piezo þ waveguide connection to Cry. Ho. Lab þ analog A/phi klystron loop and: þ fully-automated LFD compensation system (from CERN) S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
Simulation of the LLRF in pulsed mode: O. Piquet S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
Preparation of RF tests in pulsed mode Objective of the tests: § Study and development of a correction algorithm of the Lorentz Force Detuning able to limit the variation of the phase during the beam pulse in order to achieve more easily the required field stability § Implementation and measurement in pulsed mode on a real sc cavity Operation of the cavity b=0. 47 in pulsed mode Filling time=300 ms, flat top=1 ms, frep=50 Hz Qex = 1. 106 , Eacc= 13 MV/m 4 x. Pflat=230 k. W Pklystron tcav ln 2 4 x. Pflat top generation Pflat 4 × tcav ln 2 Eacc= 13 MV/m @ Qo=1 e 10 S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009 Vcavity time
Preparation of RF tests in pulsed mode What is needed and (almost) available: Ø b=0. 47 sc cavity quenching above 13 MV/m Ø LFD compensation system (with manual tuning of PZT drive pulse i. e. pre-delay, amplitude and rise time) Ø RF power generator (> 250 k. W) Ø Horizontal cryostat Ø Helium liquefier, compressor, pumping system Ø coupler processed above 250 k. W in SW Ø tuning system with piezo Ø analog A/phi klystron loop Ø fully-automated LFD compensation system (from CERN) S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009
Preparation of RF tests in pulsed mode RF power test stand Horizontal cryostat Bench for coupler processing S. Chel SLHC-PP meeting, CERN, 25 -26 February 2009 b=0. 47 sc cavity


