Automatic Identification Technology IV Contract W 91 QUZ-09 -D-0044 Project Progress Review (PPR) #7 24 August 2010 COMPANY CONFIDENTIAL
Agenda • Status of current technological substitutions and additions; • Status of configuration and risk management activities; • Status of Task Orders, Delivery Orders and purchase card • • orders, Actions under warranty and maintenance; Significant trends (quantities by CLIN, component reliability safety issues, problems, and recommended solutions); Minutes from the previous PPR; Activities determined to be of importance to the Government, such as unanticipated problems, and high visibility issues identified by the Government; Status of significant program events; Customer feedback; Agencies and organizations contacted and initiatives with each; COMPANY Reason for delinquent Task Orders, Delivery Orders, and Slide 2 CONFIDENTIAL
Intermec AIT-IV Program Team Tom Glen Director, Federal Sales Public Sector 571 -438 -3153 Trenita Nowlin Sr. Admin. Assistant (Contractor) 703 -418 -0382 Sean Langham Mgr, SE Team 703 -628 -3181 Vacant Sr. Mgr, Bus. Development Dave Boppell Systems Engineer – Navy & MC 484 -497 -6171 Darin Delaney Systems Engineer – Army 281 -651 -0455 Sam Matchey Systems Engineer – Civilian Agencies 763 -425 -6367 Dave Stone Systems Engineer – USPS, DLA, USAF 540 -343 -7129 Larry Huseby Director, Bus. Development 425 -356 -1828 Ron Payne Legal Counsel/Contracts 425 -348 -2756 Pete Rouse Channel Business Mgr Federal Sector 770 -335 -0881 Paul Dembeck Account Manager HHS & Civilian Agencies 301 -725 -1869 Don Green Account Manager Navy, /Marines 443 -458 -5599 Lars Hohmann Account Manager Civilian Agencies 410 -480 -5436 Dave Jones Account Manager Regina Keitt Program Manager AIT IV 703 -418 -0388 Vacant Public Sector Marketing Communications Mike Mc. Namara Mgr. of Professional Services Global Operations 603. 726. 3770 Ken Taylor Project Manager 770 -428 -3870 Professional Services Ron Teeters Project Manager 440 -944 -7044 Professional Services Dennis Morgan Project Manager Hardware Orders 425 -265 -2181 Shannon Landis Program Manager Technical Engr. Services 336 -227 -5985 US Air Force 757 -234 -6588 COMPANY CONFIDENTIAL George Moss Account Manager US Army 703 -608 -7894 Paul Marks Project Manager 704 -945 -8073 Professional Services Slide 3
Intermec’s Primary POCs for AIT IV COMPANY CONFIDENTIAL Slide 4
Contract Change Proposals Status CCP Description Date Submitted Status AIN 010 Updates Seagull Scientific Bar. Tender Software CLIN 0031 DA 8/17/2010 Pending Gov Review AIN 009 Change PN for DM 7500 & Removes PW Supply off CLIN 0005 AA 8/11/2010 Pending Gov Review AIN 008 Adds Configuration number to HHT w/ USB SNAP-ON CAC Substitution 8/18/2010 Pending Gov Review AIN 007 PN Change CK 3 Handle 5/18/2010 Awarded 7 June 2010 P 00008 AIN 006 Substitute HHT for BT enabled HHT w/ user Defined CAC reader 3/3/2010 Awarded Jun 11 2010 P 00007 AIN 005 Add BT HHTs Configurations 1/19/2010 Withdrawn 3/3/10 AIN 004 Modify Smalls Arms Room WSW Pricing 11/13/2009 Rejected 3/3/2010 Intermec revising AIN 003 Add Aruba 3600 11/10/2009 Awarded 21 Jan 2010 P 00004 AIN 002 Update PN CK 3 Stylus 5/18/2010 Awarded 7 June 2010 P 00008 AIN 001 Update CLIN LIST; correct PN; No change to price of configuration 08/24/2009 Rev 1 09/11/2009 Rev 2 10/29/2009 Awarded 15 Dec 2009 P 00003 COMPANY CONFIDENTIAL Slide 5
Current Technological Substitutions & Additions • CCP AIN 004 - Revising -Modify Smalls Arms Room • CCP AIN 008 - Adds configuration number for substitution HHT w/SNAP-ON CAC • CCP AIN 009 - Substitutes PN for DM 7500 CLIN 005 BA & Removes PW Supply off CLIN 0005 AA • CCP AIN 010 - Updates Seagull Scientific Bar. Tender Software PN CLIN 0031 DA COMPANY CONFIDENTIAL Slide 6
Configuration & Risk Management • Installing CAC enablement SW on HHTs • CAC enablement SW is downloadable from Intermec AIT IV website for interim • Solutions • We are working to pre-load the IA SW at time of manufacture • Note: CAC enablement SW supports both BT and USB readers COMPANY CONFIDENTIAL Slide 7
Task, Delivery & Purchase Card Orders As of 31 July 2010 COMPANY CONFIDENTIAL Slide 8
Task, Delivery & Purchase Card Orders, Cont As of 31 July 2010 • There were 2 Army Task Orders to date totaling $355, 999 (no change ) Total of Delivery Orders & Task Orders 23 July 2009 (contract start) through 31 July 2010 $2, 737, 847 COMPANY CONFIDENTIAL Slide 9
Actions Under Warranty & Maintenance • CLIN 0015 BA being replaced under Warranty • Replacement NEMA enclosure received at Intermec • Intermec performing QA COMPANY CONFIDENTIAL Slide 10
Significant Trends (Quantities by CLIN, component reliability safety issues, problems, and recommended solutions) • CLIN 0015 BA Aruba NEMA enclosure for AP • Intermec has received modified enclosure from OEM and is performing QA; • CLIN 0005 BA DM 7500 Stand • Parts estimated to OEM 2 nd week in Sep • Intermec QA 3 rd week in Sep • Projected to ship to customer end of Sep COMPANY CONFIDENTIAL Slide 11
Minutes from the previous PPR • Available on Intermec AIT website (http: //intermec. com/AIT/) COMPANY CONFIDENTIAL Slide 12
Activities Determined Importance to Government Such as unanticipated problems, and high visibility issues identified by the Government; • Ordering Catalog review completed by Gov; • Intermec has returned OC to Gov for review and acceptance COMPANY CONFIDENTIAL Slide 13
Significant Program Events • Air Force AIT/IUID Warfighter Conference 27 -29 Jul • Military Logistics Summit 13 – 16 Sep COMPANY CONFIDENTIAL Slide 14
Customer Feedback COMPANY CONFIDENTIAL Slide 15
Agencies & Organizations Contacted & Initiatives • Intermec AIT IV Road Show • Huntsville; ANAD; Norfolk NAS; RRAD; CCAD COMPANY CONFIDENTIAL Slide 16
Delinquent Task, Delivery, & Purchase Card Orders • DO 0002 all CLINS delivered except ; • CLIN 0005 BA Scanner Stand - EDD shifted to Late Sep • BA 01 Zebra Printer • OEM experiencing various parts shortages • Zebra plans to keep an inventory of printers/ parts to support the AIT IV contract in Vernon Hills facility; • EDD is EOM COMPANY CONFIDENTIAL Slide 17
Q&A COMPANY CONFIDENTIAL Slide 18