Adoption of Residential Estate Roads Sue Reynolds MSt (Cantab), MCIHT Highway Development Control Manager Chief Executive Mark Lloyd www. cambridgeshire. gov. uk
Highway Development Control Team: - • • Manager – Cambridge based 1 Business Support Officer 7 Engineers – Area Based 4 Inspectors – Area Based Chief Executive Mark Lloyd www. cambridgeshire. gov. uk
New residential estate roads serving in excess of 5 dwellings are considered for adoption under: • Section 38 of HA 1980, or • Section 37 of HA 1980 * Industrial estate roads are not adopted by CCC Chief Executive Mark Lloyd www. cambridgeshire. gov. uk
CCC does not operate the APC • Has no history of doing so, consequently under no legal duty to apply the code in Cambridgeshire • Will not consider applying, as additional staff resource that would be necessary could not be justified for unquantifiable ‘benefit’. Chief Executive Mark Lloyd www. cambridgeshire. gov. uk
S 38 Agreement: • 2 Year Agreement Period • Ability to extend the Agreement Period – – by agreement with engineer with recalculation of Bond if necessary • 12 Month Maintenance Period • Payment of Commuted Sums prior to issue of Final Certificate Chief Executive Mark Lloyd www. cambridgeshire. gov. uk
Current Bond and Fee Calculation • Bond calculated on the basis of linear metre of carriageway, footpath and cycleway. Currently: – £ 800 p/lm carriageway – £ 105 p/lm cycleway – £ 70 p/lm footpath + The value of any Commuted Sum(s) * These figures subject to yearly review. Chief Executive Mark Lloyd www. cambridgeshire. gov. uk
Inspection Fee is currently 7. 5% of the Bond Sum • 50% of the Inspection Fee is collected prior to the commencement of technical vetting of the development scheme • The remaining 50% is collected by Legal Team upon sealing of the Agreement Chief Executive Mark Lloyd www. cambridgeshire. gov. uk
Statistics: • In 5 year period 2004 -2008 an average of 42 Section 38 submissions were made per year • CCC Currently has circa 80 No residential estate developments without the benefit of S 38 Agreements • 5 No sites where there is no Section 38 in place and the developer has gone into administration Chief Executive Mark Lloyd www. cambridgeshire. gov. uk
• Whilst CCC has no legal obligation to resolve the problem, advice and attendance at resident groups is being provided on the strict understanding that no financial assistance will be forthcoming. • To date, no such development has been completed by the residents to an adoptable standard Chief Executive Mark Lloyd www. cambridgeshire. gov. uk
The Future Review of fee structure: • Following a benchmarking exercise CCC are considering imposing an Inspection Fee of 10% of the Bond which will be applied if the developer commences work prior to an Agreement being sealed. As an incentive, this will be reduced to 8% if the Agreement is sealed prior to work commencing on site. Chief Executive Mark Lloyd www. cambridgeshire. gov. uk
Resultant review of staff resource / structure: • Number of inspectors • Greater flexibility – able to respond to area pressure, and; • Software to manage the administration Chief Executive Mark Lloyd www. cambridgeshire. gov. uk
Questions? Chief Executive Mark Lloyd www. cambridgeshire. gov. uk