Administering Lump Sum P/T Contracts via a Cost Loaded Schedule Tom Wiener, P. E. Administering Lump Sum P/T Contracts via a Cost Loaded Schedule Tom Wiener, P. E. Mn. DOT Project Controls Engineer Matt Reid, P. E. HDR Engineering, Inc.

Background – Why? Background – Why?

Cost Loaded Schedule Allows for Breakdown of L. S. Cost ◦ Validate Costs of Cost Loaded Schedule Allows for Breakdown of L. S. Cost ◦ Validate Costs of the L. S. Better Quality Control Better Progress Control and Monitoring ◦ Earned Value / Revenue Techniques

Cost Loaded Schedules Schedule of Values Contractor Consultant (Low Bid Contract) Lump Sum Bid Cost Loaded Schedules Schedule of Values Contractor Consultant (Low Bid Contract) Lump Sum Bid items are Cost Accounts in P 6 that align with Unit Rate bid items

Cost Loaded Schedules Schedule of Values Contractor Consultant Challenges Faced We’ve Never Done This Cost Loaded Schedules Schedule of Values Contractor Consultant Challenges Faced We’ve Never Done This Before ($14. 2 M QBS) Office of Audit/Validation of Costs Creating Negotiated Work Packages from RFP Schedule Was a Learning Curve for Consultant

MN Earned Revenue Method • Provides Method for Equity Control • Allows for Schedule MN Earned Revenue Method • Provides Method for Equity Control • Allows for Schedule Risk to be Reduced • Reduces Fears of Lump Sum • Encourages Innovation • Scope Diligence • Streamlined Payment Administration

St. Croix Design Schedule St. Croix Design Schedule

St. Croix Design Schedule Lump Sum Contract Requirement 1 st Design Contract – Lump St. Croix Design Schedule Lump Sum Contract Requirement 1 st Design Contract – Lump Sum CPM Use of Mn. DOT SWIFT Codes ◦ ◦ ◦ 1010 – Project Management 1250 – Misc. Engineering & Support 2824 – Special Studies ABUT DECK PIER Oracle Primavera P 6

Types of Schedules Baseline Schedules – 1 st plan for executing work and progress Types of Schedules Baseline Schedules – 1 st plan for executing work and progress measured from Update Schedules – record of progress on a monthly basis; actual dates, remaining durations, actual cost, earned value. Revised Schedules – Re Baseline if necessary

St. Croix Baseline Development Schedule built locally Coordination with Functional Leads and Mn. DOT St. Croix Baseline Development Schedule built locally Coordination with Functional Leads and Mn. DOT Baseline Acceptance Baseline Uploaded to Mn. DOT Hosted P 6 Environment

St. Croix - Work Breakdown Structure (WBS) St. Croix - Work Breakdown Structure (WBS)

Mn. DOT CPM Specifications Similar to Mn. DOT CPM Const Specs – 1803 Activity Mn. DOT CPM Specifications Similar to Mn. DOT CPM Const Specs – 1803 Activity Durations 5 -20 days Activity must have Predecessor/Successor No Lags/Leads Constraints Contract Time, Delays, Impacts, Failure to complete work on time

St. Croix Scheduling Schedule Activities – 465 Logic Relationships – 750 Constraints – 14 St. Croix Scheduling Schedule Activities – 465 Logic Relationships – 750 Constraints – 14 Initially, 2 Afterward Critical Activities – 40, less than 10% of Project, no more than 30% per spec

Assigning Cost Accounts to Activities- Cost Loading SWIFT Codes Differentiate Subs – Multiple Entries Assigning Cost Accounts to Activities- Cost Loading SWIFT Codes Differentiate Subs – Multiple Entries Reporting

Schedule Updates – Earned Value Schedule Updated Monthly ◦ Purposes of CPM ◦ Coordination Schedule Updates – Earned Value Schedule Updated Monthly ◦ Purposes of CPM ◦ Coordination with Design Functional Leads ◦ Schedule Narrative Highlights Anticipated/Final Milestones Critical Coordination Activities Change in Schedule Logic ◦ Payment - Invoicing

Schedule Updates – Invoicing Schedule Updates – Invoicing

Benefits of Design CPM on St. Croix Organization Communication Analysis ◦ Define deliverables in Benefits of Design CPM on St. Croix Organization Communication Analysis ◦ Define deliverables in an organized format ◦ Ensure all contracted deliverables are accounted for ◦ Activities have agreed upon budget ◦ Relationship between disciplines and other parties ◦ Responsibility - activities are assigned to companies, DOT ◦ When deliverables are required logically ◦ On time – baseline comparison and float analysis ◦ On budget – Internal earned value/percent complete analysis ◦ Risk or Impact mitigation – All parties can identify and mitigate potential risks, allocate or shift resources

Consultant Contract Was it worth it? Yes • Validated Scope of Work • Consultant Consultant Contract Was it worth it? Yes • Validated Scope of Work • Consultant buy-in to the process • Truly managed schedules (Earned Revenue Mngt) • We needed this design done on time • Streamlined Payment administration – Auditing History

Where Are We At/Going? Project In Construction Phase Contractor’s build schedule in our network Where Are We At/Going? Project In Construction Phase Contractor’s build schedule in our network 1/1/13 Piloting BIM and CTD schedules 3/1/13 Select Unit Rate project Resource and Cost Loaded 3/1/13 Role and Resource Loaded of CE&I staff 6/1/14 Projects in Scoping and Design Phase Programmed Projects Role and Resource Loaded 6/30/13 All planned projects Role loaded by June 30, 2014 Taxpayer Transportation Accountability Act

Q&A? Administering Lump Sum P/T Contracts via a Cost Loaded Schedule Tom Wiener, P. Q&A? Administering Lump Sum P/T Contracts via a Cost Loaded Schedule Tom Wiener, P. E. Mn. DOT Project Controls Engineer Matt Reid, P. E. HDR Engineering, Inc.