ABP/RTL • Main RTL Activities for 2007/8: – Shutdown Co-ordination and Planning for PSB, PS, LEIR, TT 2, AD, SPS, TT 40 & TI 8 – CTF 3 and CLEX installation – 3 Me. V test stand installation – LHC Installation (Including TI 2) – Preparation for LINAC 4 construction – AB Consolidation project – TSO support for accelerators and service buildings 1/6/2007 ABP group meeting
ABP/RTL Simon Baird Section Leader & AB Consolidation Raymond Brown PS Sven De Man PSB & LHC Installation Nicolas Gilbert SPS, TT 40, TI 2 & TI 8 Christian Lacroix LEIR, TT 2, AD & 3 Me. V test stand José Monteiro CTF 3, CLEX* & Planning support Bernard Pires SPS Surface buildings Rosario Principe PS, 3 Me. V test stand & LINAC 4 Michel Samson SPS, TI 2 installation, AB Space Management for ADM * (CLIC Experimental Area) 1/6/2007 ABP group meeting
Shutdown/Installation Co-ordination • 2006/7 Shutdown – 8 PS main magnets renovated & re-installed – Some MTE preparatory work was completed but the main MTE work will still take place in the 2007/8 shutdown – 76 SPS main magnet water manifolds repaired – INB cable loop installed at the SPS – Major tunnel repairs in TT 2 – New beam stopper in BTP line – PSB main magnet water cooling renovation – CTF 3 Combiner ring ejection line completed – CLEX building completed (June 07) 1/6/2007 ABP group meeting
Shutdown/Installation Co-ordination • 2007/8 Shutdown (Minimum length = 12 weeks) – MTE installation • Essential for full CNGS beam operation – – PS Main magnet renovation (8 units? ) SPS main magnet manifold repairs (80 planned) Move 8 PSB wire scanners? 3 Me. V test stand installation • CTF – Installation of CLEX equipment – Installation of the TL 2 line (from the Combiner Ring to the CLEX) • LINAC 4 – Choice of site – Technical coordination for the project 1/6/2007 ABP group meeting
• AB Consolidation – There are 44 active Work Units in 2007 • By the end of 2007 a total of 36. 8 MCHF will/should have been spent (total budget at present is 50 MCHF ) – A full review of all outstanding Consolidation items has been completed: • White Paper request for 27 MCHF & 70 FTE’s • Waiting for the “green light” • TSO’s for Accelerators and the Service Buildings • LHC activities – One RTL section member is detached (60%) to TS for the Coordination of LHC installation activities – TI 2 installation and commissioning coordination – No decision on “How an LHC shutdown will be managed” 1/6/2007 ABP group meeting